AGHIA VARVARA STATION
The following works are in progress:
- Wall and columns cladding (metal, glass etc.)
- Square reinstatement (granites, passageways)
- Signage, signalling and lighting
- Other reinstatement works at street level
- Station signs and other signs.
MEGALOU ALEXANDROU SHAFT
The following works are still pending:
- Planting (street level).
TAXIARCHON SHAFT
The following works are in progress:
- Painting works
- Configuration at street level.
KORYDALLOS STATION
The following works are in progress:
- Wall and Columns cladding
- Installation of false ceilings
- Installation of balustrades
- Installation of roller shutters
- Installation of irrigation system at street level
- Installation of signage
- Installation of stainless steel structures
- Repair of painted surfaces and worn granites
- Installation of Station entrances’ sheds
- Installation of lift at street level
- Configuration at street level (Eleftherias Square)
PISSIDIAS SHAFT
Works have been completed.
NIKEA STATION
MAIN STATION
The following works are in progress:
- Re-painting of cylindrical supports at level -3 of the platforms
- Re-painting of technical rooms at various Station levels
- Lining of roller shutter (ETALBOND) at the shed of the central entrance
- Cladding of vertical items using metal panels
- False ceilings
- Installation of signage
- Construction of sheds at the natural light shafts.
PIRAEUS STATION
STATION
The following works have been completed:
- Installation and prestressing of struts for temporary retaining up to level 5.
- Installation of waterproofing and concreting of the foundation (bay 4).
The following works are in progress:
- Installation of reinforcement and concreting at section 1
- Station excavation at sections 2, 3 and 5 a, b (last phase)
- Improvement and installation of waterproofing and reinforcement at sections 2, 3.
- Installation and pre-loading of 4 struts of the temporary retaining at level 6.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are still pending:
- Door installation at the E/M floor.
The following works are in progress:
- Masonry walls at ticketing level
- Waterproofing at street level
- Backfilling – compaction related works
- Construction of bases of machinery at the E/M floor
- Cleaning works
UNDERGROUND PART OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, parapet walls and platform slab.
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and works related to secondary concreting.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining and secondary concrete.
The following works are in progress:
- Waterproofing of the top of the open trench.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
- Secondary concrete at the staircases.
The following works are put on hold:
- Secondary concrete at the access gallery.