Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

February 2020

NOMARCHIA Station (station & crossover): In progress are the works for the installation of granites at the platform level, as well as the works related to sewage, earthing of electric trays and piping of the lighting network, power distribution and low voltage (weak currents) networks.

KALAMARIA Station: In progress are piping works of the lighting network, power distribution and low voltage networks.

ARETSOU Station: Tunnel ventilation equipment related works are in progress.

NEA KRINI Station: In progress are the works for the reinstatement at street level, the relocation of PUO networks, the installation of earthing of electric trays, works for the installation of piping for the lighting network and works for the installation of lighting fixtures in technical rooms.

MIKRA Station (Station & Crossovers): In progress are surface reinstatement works, works for the installation of fibre-cement boards and works for supporting water supply, sewage and fire fighting networks.

TBM tunnels: The works for the construction of trackwork at a tunnel section are in progress.

WCAG