Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

APRIL 2020

AGHIA VARVARA STATION

 The following works are in progress:

  • Wall and columns cladding (metal, glass etc.)
  • Square reinstatement (installation of marbles)
  • Other reinstatement works at street level
  • Station signs and other signs
  • Installation of metal false ceilings
  • Architectural finishes (installation of balustrades and handrails)
  • Other architectural finishes.

MEGALOU ALEXANDROU SHAFT

The following works are still pending:

  • Planting (street level).

TAXIARCHON SHAFT

The following works are in progress:

  • Painting works
  • Configuration at street level.

KORYDALLOS STATION

The following works are in progress:

  • Wall and Columns cladding
  • Installation of false ceilings
  • Installation of balustrades
  • Installation of roller shutters
  • Installation of irrigation system at street level
  • Installation of signage
  • Installation of stainless steel structures
  • Repair of painted surfaces and worn granites
  • Installation of Station entrances’ sheds
  • Installation of lift at street level
  • Configuration at street level (Eleftherias Square)

NIKEA STATION

MAIN STATION

The following works are in progress:

  • Treatment and re-painting of industrial floors in E/M areas
  • Installation of sheds’ metal frame at the natural light shaft
  • Cladding of vertical items using metal panels
  • False ceilings
  • Preliminary works for the installation of stainless steel handrails at the escalators in the concourse area.

NATM TUNNEL FOR STATION VENTILATION

The following works have been completed:

  • Construction of the final lining
  • Painting works (still pending are painting works at the connection with TBM tunnel)
  • Construction of industrial floor.

MANIATIKA STATION

STATION’s C/C

The following works have been completed:

  • Waterproofing of perimeter paramet walls
  • Permanent lining of the foundation (level -4)
  • Permanent lining of E/M slab (level -3)
  • Permanent lining of the ticketing area slab (level -2)
  • Permanent lining of staircace S4
  • Permanent lining of E/M slab (level -1).

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Permanent lining of the station’s main tunnel
  • Permanent lining of the deepening area
  • Permanent lining of the northern and southern headwall
  • Construction of parapet walls and platform slabs
  • Secondary grouting of the vault of the main station tunnel.

PIRAEUS STATION 

STATION

The following works have been completed:

  • Installation and prestressing of struts for temporary retaining up to level 5.
  • Installation of waterproofing underneath the foundation at bays 1, 2, 3, 4 (still pending is the pumping station)
  • Concreting of the foundation slab at sections 1, 4.

The following works are in progress:

  • Installation of the foundation slab’s reinforcement and concreting at sections 2, 3 and 5N
  • Excavation of the station, section 5B (last phase) and of the pumping station
  • Improvement and installation of waterproofing at sections 5N and 5B
  • Installation of reinforcement at the foundation slab at section 5B
  • Concreting of platform walls at bays 1 and 2
  • Concreting of the non reinforced concrete filling at bays 5N, 2 and 3
  • Installation and pre-loading of 10 struts of the temporary retaining at level 6.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works are still pending:

  • Door installation at the E/M floor.

The following works are in progress:

  • Brick structures at the ticketing and platform levels
  • Waterproofing at street level
  • Plastering works at the platform level
  • Cleaning works

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

 The following works have been completed:

  • Concreting of the permanent lining, secondary concrete and waterproofing.

The following works are in progress:

  • Waterproofing of the top of the open trench.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

 The following works have been completed:

  • Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
  • Secondary concrete at the staircases.

The following works are put on hold:

  • Secondary concrete at the access gallery.

 The following works are in progress:

  • Removal of the 2nd row of metal struts

 RALLIOS SHAFT – VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining.

 

WCAG