AGHIA VARVARA STATION
The following works are in progress:
- Wall and columns cladding (metal, glass etc.)
- Square reinstatement (installation of marbles)
- Other reinstatement works at street level
- Station signs and other signs
- Installation of metal false ceilings
- Architectural finishes (installation of balustrades and handrails)
- Other architectural finishes.
MEGALOU ALEXANDROU SHAFT
The following works are still pending:
- Planting (street level).
TAXIARCHON SHAFT
The following works are in progress:
- Painting works
- Configuration at street level.
KORYDALLOS STATION
The following works are in progress:
- Wall and Columns cladding
- Installation of false ceilings
- Installation of balustrades
- Installation of roller shutters
- Installation of irrigation system at street level
- Installation of signage
- Installation of stainless steel structures
- Repair of painted surfaces and worn granites
- Installation of Station entrances’ sheds
- Installation of lift at street level
- Configuration at street level (Eleftherias Square)
NIKEA STATION
MAIN STATION
The following works are in progress:
- Treatment and re-painting of industrial floors in E/M areas
- Installation of sheds’ metal frame at the natural light shaft
- Cladding of vertical items using metal panels
- False ceilings
- Preliminary works for the installation of stainless steel handrails at the escalators in the concourse area.
NATM TUNNEL FOR STATION VENTILATION
The following works have been completed:
- Construction of the final lining
- Painting works (still pending are painting works at the connection with TBM tunnel)
- Construction of industrial floor.
MANIATIKA STATION
STATION’s C/C
The following works have been completed:
- Waterproofing of perimeter paramet walls
- Permanent lining of the foundation (level -4)
- Permanent lining of E/M slab (level -3)
- Permanent lining of the ticketing area slab (level -2)
- Permanent lining of staircace S4
- Permanent lining of E/M slab (level -1).
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Permanent lining of the station’s main tunnel
- Permanent lining of the deepening area
- Permanent lining of the northern and southern headwall
- Construction of parapet walls and platform slabs
- Secondary grouting of the vault of the main station tunnel.
PIRAEUS STATION
STATION
The following works have been completed:
- Installation and prestressing of struts for temporary retaining up to level 5.
- Installation of waterproofing underneath the foundation at bays 1, 2, 3, 4 (still pending is the pumping station)
- Concreting of the foundation slab at sections 1, 4.
The following works are in progress:
- Installation of the foundation slab’s reinforcement and concreting at sections 2, 3 and 5N
- Excavation of the station, section 5B (last phase) and of the pumping station
- Improvement and installation of waterproofing at sections 5N and 5B
- Installation of reinforcement at the foundation slab at section 5B
- Concreting of platform walls at bays 1 and 2
- Concreting of the non reinforced concrete filling at bays 5N, 2 and 3
- Installation and pre-loading of 10 struts of the temporary retaining at level 6.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are still pending:
- Door installation at the E/M floor.
The following works are in progress:
- Brick structures at the ticketing and platform levels
- Waterproofing at street level
- Plastering works at the platform level
- Cleaning works
UNDERGROUND PART OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, parapet walls and platform slab.
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and works related to secondary concreting.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concrete and waterproofing.
The following works are in progress:
- Waterproofing of the top of the open trench.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
- Secondary concrete at the staircases.
The following works are put on hold:
- Secondary concrete at the access gallery.
The following works are in progress:
- Removal of the 2nd row of metal struts
RALLIOS SHAFT – VENTILATION TUNNEL
The following works have been completed:
- Concreting of the permanent lining.