AGHIA VARVARA STATION
The following works are in progress:
- Wall and columns cladding (metal, glass etc.)
- Reinstatement works at street level (passageways, marbles)
- Other reinstatement works at street level
- Installation of metal false ceilings
- Architectural finishes (installation of balustrades and handrails)
- Installation of lifts at street level.
MEGALOU ALEXANDROU SHAFT
The following works are still pending:
- Planting (street level).
TAXIARCHON SHAFT
The following works are in progress:
- Painting works
- Configuration at street level.
KORYDALLOS STATION
The following works are in progress:
- Wall and Columns cladding
- Installation of false ceilings
- Installation of balustrades
- Installation of irrigation system at street level
- Installation of signage
- Installation of stainless steel structures
- Repair of painted surfaces and worn granites
- Installation of Station entrances’ sheds
- Configuration at street level (Eleftherias Square).
NIKEA STATION
MAIN STATION
The following works are in progress:
- Wall cladding with metal panels
- Cladding and handrails for escalators
- False ceilings
- Glass barriers in public areas
- Replacement of floor paving slabs at street level.
NATM TUNNEL FOR STATION VENTILATION
The following works have been completed:
- Construction of the final lining
- Painting works (still pending are painting works at the connection with TBM tunnel)
- Construction of industrial floor.
MANIATIKA STATION
STATION’s C/C
The following works have been completed:
- Waterproofing of perimeter paramet walls
- Permanent lining of the foundation (level -4)
- Permanent lining of E/M slab (level -3)
- Permanent lining of the ticketing area slab (level -2)
- Permanent lining of staircace S4
- Permanent lining of E/M slab (level -1)
- Permanent lining of perimeter walls and columns.
The following works are in progress:
- Permanent lining of the roof slab and staircase S3.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Permanent lining of the station’s main tunnel
- Permanent lining of the deepening area
- Permanent lining of the northern and southern headwall
- Construction of parapet walls and platform slabs
- Secondary grouting of the vault of the main station tunnel.
The following works are in progress:
- Filling of platform ducts with non-reinforced concrete.
PIRAEUS STATION
STATION
The following works have been completed:
- Installation and prestressing of struts for temporary retaining up to level 5 and of 14 out of 17 struts at level 6.
- Installation of waterproofing underneath the foundation at bays 1, 2, 3, 4 (still pending is the pumping station)
- Concreting of the foundation slab at sections 1, 4.
The following works are in progress:
- Installation of the foundation slab’s reinforcement and concreting at sections 5N and 5B and in the pumping station area. Completion of concreting of the foundation slab of the main station.
- Excavation in the area of the station’s pumping station. Completion of the excavation of the main station.
- Concreting of parapet walls underneath the platforms and of the non reinforced concrete filling at bays 2, 3, 5N and 35B.
- Installation and pre-loading of 10 struts of the temporary retaining at level 6.
- Installation of waterproofing underneath the foundation in the area of the pumping station. Completion of the waterproofing of the main station’s foundation.
- Removal of the 5th and 6th rows of struts in progress.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works are still pending:
- Door installation at the E/M floor.
The following works are in progress:
- Conservation of the Project’s archaeological finds
- Brick structures at the ticketing and platform levels
- Preliminary works for roof painting at platform level
- Cleaning works.
UNDERGROUND PART OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, parapet walls and platform slab.
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and works related to secondary concreting.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concrete and waterproofing.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
- Secondary concrete at the staircases.
The following works are put on hold:
- Secondary concrete at the access gallery.