NEW RAILWAY STATION: The works for the construction of the filling concrete in the area of the forestation are in progress.
DIMOKRATIAS Station: The works for the installation of a sewage network are in progress.
VENIZELOU Station: The works for the removal of struts and monorail installation are in progress.
PANEPISTIMIO Station: The works for the installation of gas equipment in tunnels are in progress.
EFKLIDIS Station: The works for the installation of a third rail in track 1 are in progress.
NEA ELVETIA Station: The works for the reinstatement of escalators are in progress.
DEPOT:
Building Complex Ι: The works for the construction of tiles at the washing plant have been completed. Works for the configuration of the surrounding area are in progress.
Building Complex ΙΙ: The installation of lifts 2.2 has been completed while the installation of the water supply network is in progress.
ΤΒΜ Tunnels: Trackwork construction works in a section of the project tunnels are in progress.