Kritis Shaft: The works for the construction of masonry walls and plastering works have been completed, while the works for door installation are in progress.
NOMARCHIA Station: In progress are the works for the installation of glass doors at platform level and of windows in rooms 2.2 & 2.3, as well as the works related to fire detection, fire fighting and sewage.
KALAMARIA Station: In progress are reinstatement works at street level, as well as works related to the installation of the fire rated air ducts’ network, the sewage network and the lighting networks’ cabling.
ARETSOU Station: The works for the installation of galvanized balustrades and handrails have been completed, while in progress are colouring works in public areas. Moreover, in progress are works for the installation of earthing, of the lighting networks’ cabling and for the installation of lighting fixtures in technical rooms.
NEA KRINI Station (station and crossovers): Lining related works using sidewalk slabs, as well as works for the installation of balustrades and handrails are in progress. In the 1st crossover area, works for the installation of balustrades and handrails are in progress.
MIKRA Station: The works for the installation of balustrades and handrails are in progress.
Trackwork: In progress are sleepers distribution related works on track 1 from KALAMARIA Station up to KP 2+800, track assembly and welding related works on track 2 from KP 0+091 up to NOMARCHIA Crossover, as well as concreting works on tracks 1 & 2 from KP 2+800 up to the 2nd Crossover of MIKRA Station.