MANIATIKA STATION
STATION’s C/C
The following works have been completed:
- Waterproofing of perimeter parapet walls
- Permanent lining of the foundation (level -4)
- Permanent lining of E/M slab (level -3)
- Permanent lining of the ticketing area slab (level -2)
- Permanent lining of staircace S4
- Permanent lining of E/M slab (level -1)
- Permanent lining of perimeter walls and columns
- Permanent lining of the roof slab and staircase S3
- Construction of perimeter walls of the station’s main entrance (at street level) and of the inclined part of the main entrance (shed).
The following works are in progress:
- Waterproofing of the roof slab
- Construction of masonry walls and execution of plastering works at levels -4,-3 and -1.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Permanent lining of the station’s main tunnel
- Permanent lining of the deepening area
- Permanent lining of the northern and southern headwall
- Construction of parapet walls and platform slabs
- Secondary grouting of the vault of the main station tunnel
- Filling of platform ducts with non-reinforced concrete.
PIRAEUS STATION
The following works have been completed:
- Concreting of the foundation slab and placing of non-reinforced concrete over the foundation.
The following works are in progress:
- Installation of waterproofing of the station’s parapet walls and in areas of the north and south front
- Concreting of the station’s perimeter walls and of the walls underneath the platforms
- Concreting of platform slabs
- Re-installation of the 5th row of struts at a new location and removal of the 3rd and 4th rows of struts
- Concreting of slab at level -2 (section 4).
ROLOI SHAFT
The following works have been completed:
- Construction of foundation and permanent lining of perimeter walls (still pending is the termination at street level).
The following works are in progress:
- Construction of intermediate parapet wall (up to +1.50) and staircase (down to -1.70).
NATM ACCESS TUNNEL
The following works have been completed:
- Concreting of the permanent lining.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station.
The following works are in progress:
- Cleaning works
- Preliminary works for roof painting at platform level
UNDERGROUND PART OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, parapet walls and platform slab.
The following works are in progress:
- Preliminary works for painting the vault.
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and works related to secondary concreting.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concrete and waterproofing.
The following works are in progress:
- Backfilling – compaction related works in C/C.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
- Secondary concrete at the staircases.
The following works are put on hold:
- Secondary concrete at the access gallery.
DELIGIANNI SHAFT
The following works have been completed:
- Excavation and temporary retaining up to the final level
- Waterproofing, construction of foundation slab and perimeter parapet walls down to -3.0.
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works have been completed:
- Excavation – temporary retaining
- Concreting of the foundation of the shaft’s permanent lining
- Concreting of floor and parapet walls of the permanent lining of the connecting tunnel.
The following works are in progress:
- Concreting of the vault of the connecting tunnel.