Kritis Shaft: Preparatory works for street-level reinstatement are in progress.
NOMARCHIA Station: In progress are works for the installation of windows in rooms 2.2 & 2.3, as well as earthing works and works for the installation of air duct networks for HVAC system.
KALAMARIA Station: In progress are works for the installation of windows in rooms 2.2 & 2.3, as well as earthing works and cabling works for the lighting network.
PONTOU Shaft: In progress are works for the construction of industrial floors, as well as reinstatement works at street level.
NEA KRINI Station: In progress are escalators’ testing and setting works.
MIKRA Station: Preliminary works for street-level reinstatement at the 2nd Crossover are in progress.
Trackwork: In progress are sleepers distribution related works on track 2 and rail assembly and welding related works on track 1 from KALAMARIA Station up to KP 2+800. Moreover, in progress are sleepers distribution related works on tracks 1 and 2, rail assembly and welding related works on track 1 from NOMARCHIA Crossover up to KALAMARIA Station, as well as concreting works on tracks 1 & 2 from KP 2+800 up to the 2nd Crossover.