- NOMARCHIA Station: The works for the installation of a steel emergency escape hatch have been completed, while in progress are works for the installation of HVAC equipment.
- KALAMARIA Station: In progress are works for the construction of network-related infrastructure and works for the implementation of traffic regulations -phase H. In progress are works for the installation of balustrades in technical rooms.
- ARETSOU Station: Earthing and lighting network cabling works are in progress.
- PONTOU Shaft: In progress are works for the construction of industrial flooring and street-level reinstatement works.
- NEA KRINI Station: In progress are works for the construction of water supply and fire fighting pits and sound proofing works.
- MIKRA Station: In progress are works for the installation of balustrades and handrails.
TRACKWORK: The works for the assembly of tracks and welding works on Track 2 from KALAMARIA Station up to K.P. 2+800 and from NOMARCHIA Crossover up to KALAMARIA Station have been completed. Moreover, concreting works on tracks 1 & 2 from K.P. 2+800 up to the 2nd Crossover (except for MIKRA Station) and from the 2nd Crossover up to the Forestation have been completed.