Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

NOVEMBER 2020

Aghia Varvara

 

TZAVELA SHAFT

The following works have been completed:

  • Permanent lining of the bottom of the shaft
  • Permanent lining of the connecting tunnel
  • Removal of temporary steel frames for the support of the TBM tunnel
  • Permanent lining of the perimeter wall of the shaft
  • Permanent lining of interior parapet wall and staircase
  • Permanent lining of the slab at level +8.57

 MANIATIKA STATION

STATION’s C/C

The following works have been completed:

  • Waterproofing of perimeter parapet walls
  • Permanent lining of the foundation (level -4)
  • Permanent lining of E/M slab (level -3)
  • Permanent lining of the ticketing area slab (level -2)
  • Permanent lining of staircace S4
  • Permanent lining of E/M slab (level -1)
  • Permanent lining of perimeter parapet walls and columns
  • Permanent lining of the roof slab and staircase S3
  • Construction of perimeter parapet walls of the station’s main entrance (at street level) and of the inclined part of the main entrance (shed).

The following works are in progress:

  • Waterproofing of the roof slab
  • Construction of masonry walls and execution of plastering works at levels -4,

-3, -2 and -1.

  • Construction of secondary concrete parapet walls at level -1.
  • Construction of waterproofing – permanent lining of the eastbound station lift

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Permanent lining of the station’s main tunnel
  • Permanent lining of the deepening area
  • Permanent lining of the northern and southern headwall
  • Construction of parapet walls and platform slabs
  • Secondary grouting of the vault of the main station tunnel
  • Filling of platform ducts with non-reinforced concrete.

The following works are in progress:

  • Repair works of the station’s concrete vault and painting works at level -5.

PIRAEUS STATION 

The following works have been completed:

  • Waterproofing works under the foundation
  • Concreting of the foundation slab and placing of non-reinforced concrete over the foundation.
  • Concreting of platforms and vertical elements underneath the platforms.

The following works are in progress:

  • Installation of waterproofing at the station’s perimeter parapet walls
  • Concreting of the station’s perimeter parapet walls
  • Installation of formwork and reinforcement at the ticketing area slab
  • Concreting of the ticketing area slab
  • Removal of struts and sleepers of the 2nd and 5th rows
  • Concreting of inner parapet walls and columns

ROLOI SHAFT

The following works have been completed:

  • Construction of foundation and permanent lining of perimeter parapet walls (still pending is the termination at street level).

The following works are in progress:

  • Construction of the door frame and installation of roller shutter.

NATM ACCESS TUNNEL

The following works have been completed:

  • Concreting of the permanent lining.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are put on hold:

  • Installation of doors at E/M level.

The following works are in progress:

  • Cleaning works
  • Painting works at the concourse and E/M levels
  • Cement mortar laying works at the platform level
  • Conservation of the archaeological finds of the Project.

UNDERGROUND PART OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining, parapet walls and platform slab.

The following works are in progress:

  • Cement mortar laying works at the platform level.

 STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and works related to secondary concreting.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete and waterproofing.

The following works are in progress:

  • Backfilling – compaction related works.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Waterproofing and concreting of the permanent lining (still pending is the waterproofing detail at the terminating point, at street level)
  • Secondary concrete at the staircases.

The following works are put on hold:

  • Secondary concrete at the access gallery.
  • Backfilling – compaction related works.

 DELIGIANNI SHAFT

 The following works have been completed:

  • Excavation and temporary retaining up to the final level
  • Waterproofing, construction of foundation slab and perimeter parapet walls down to -3.0.

 PANEPISTIMIO SHAFT & VENTILATION TUNNEL

 The following works have been completed:

  • Excavation – temporary retaining
  • Concreting of the foundation of the shaft’s permanent lining
  • Concreting of the permanent lining of the connecting tunnel.

The following works are in progress:

  • Installation of reinforcement for the permanent lining and construction of formwork for the perimeter parapet walls, at the connection point between the connecting tunnel and the shaft.
WCAG