- DIMOKRATIAS Station: In progress are works for the installation of the air duct network at level -2.
- VENIZELOU Station: Diaphragm walls construction works at the southern access, as well as works related to roof slab supporting piles have been completed.
- AGHIA SOFIA Station: Works for the construction of parapet walls’ terminations at the south access are in progress.
- FLEMING Station: In progress are works at the installation of Uninterrupted Power Supply (UPS) equipment for the telecommunications and signaling systems.
- ANALIPSI Station: Works for the installation of traction power supply related equipment and cabling are in progress.
- 25 MARTIOU Station: The works for the installation of fire-rated air ducts (OTE/SAF) at track level have been completed, while the works for the installation of platform screen doors are in progress.
- VOULGARI Station: In progress are works for the installation of cable trays, as well as waterproofing and painting related works of the station’s pumping station.
DEPOT
Building Complex Ι: In progress are works for the installation of cable trays at level +74.00 and works for the installation of the lighting system at level +63.50.
Building Complex ΙΙ: In progress are works for the installation of fire detection networks at level +53.00, the installation of the lighting system at levels +52.00 and +58.00, as well as false ceilings’ construction works at level +52.00 of section V.
TRACKWORK:
The works for the construction of the floating slab of track 1 between SINTRIVANI and PANEPISTIMIO Stations have been completed. Moreover, in progress are alignment works and works for the installation of signalling equipment between SINTRIVANI and FLEMING Stations.