December 2020

KALAMARIA_12_20_1

 

  • Kritis Shaft: Reinstatement related works at street level, painting works and works related to the completion of door installation are in progress.
  • KALAMARIA Station: In progress are reinstatement related works at street level, as well as works for the installation of glass panels of the sheds at the east entrance.
  • ARETSOU Station: In progress are works for the installation of trays, as well as works for the installation of cabling for the lighting networks.
  • MIKRA Station: Surface reinstatement works are in progress.

 

TRACKWORK: Concreting works at tracks 1 and 2, from K.P. 0+091 to Nomarchia Crossover have been completed, while in progress are the respective works at tracks 1 and 2, from K.P. 2+800 to KALAMARIA Station.