ΒΑΣΙΚΟ ΕΡΓΟ - ΙΑΝΟΥΑΡΙΟΣ 2021

 

 

  • DIMOKRATIAS STATION: Works related to the installation of fire fighting, sewage and water supply networks at level -2 have been executed.
  • AGHIA SOFIA Station: Preparatory works for the construction of masonry at levels -2 and -3 are in progress.
  • SINTRIVANI Station: The works for the installation of sub-frames to support the platform air duct inlets, the works for the installation of traction power equipment and cables, as well as cabling related works for PSDs have been completed.
  • PANEPISTIMIO Station: The works for the construction of the platform filling concrete have been completed. The works for the installation of ventilation & A/C related equipment are in progress.
  • EFKLIDIS Station: The works for the installation of Traction Power equipment and cables have been completed. In progress are preparatory works for the construction of platform filling concrete, as well as works for the installation of cabling related to the data communication system.
  • 25 MARTIOU Station: The works for the installation of equipment related to traction power supply, signaling and telecommunications are in progress.
  • VOULGARI Station: In progress are works for the installation of equipment related to traction power supply, signaling and telecommunications.
  • NEA ELVETIA Station: The works for the installation of traction power supply equipment are in progress.

DEPOT

Building Complex Ι: In progress are building works at levels +52.00 and +58.00, as well as works for the installation of floor-built in sockets at level +69.00.

Building Complex ΙΙ: In progress are works for the installation of piping related to the ventilation and A/C network at levels +53.00 and +62.30, as well as of piping related to the automatic extinguishing network using gas at level +62.30.

TRACKWORK: Completed are the works for the construction of the floating slabs between ANALIPSI and 25 MARTIOU Stations, as well as the works for the construction of the floating slabs/turnovers at 25 MARTIOU crossover. Moreover, in progress are works for the completion of the installation of prefabricated cable ducts and for the installation of the 3rd rail.