MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Completion of the permanent lining of the shaft
The following works are in progress:
- Waterproofing of the roof slab
- Masonry walls – plastering works at levels -4, -3, -2 and -1
- Architectural finishes – Painting works at level -4
- Industrial flooring at levels -4, -3 and -2
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Permanent lining of the station’s main tunnel
- Permanent lining of the deepening area
- Permanent lining of the northern and southern headwall
- Construction of parapet walls and platform slabs
- Secondary grouting of the vault of the main station tunnel
- Filling of platform ducts with non-reinforced concrete.
The following works are in progress:
- Repair works of the station’s concrete vault and painting works at level -5.
PIRAEUS STATION
The following works have been completed:
- Waterproofing works underneath the foundation and at the perimeter walls
- Concreting of platform and vertical parapet walls underneath the platforms.
- Concreting of perimeter walls, inner parapet walls, intermediate slabs and columns
The following works are in progress:
- Removal of struts and walers of the 1st row
- Installation of formwork, reinforcement and concreting of the roof slab
- Commencement of architectural finishes – construction of masonry walls and performance of plastering works
ROLOI SHAFT
The following works have been completed:
- Construction of permanent lining (still pending is the termination at street level).
NATM ACCESS TUNNEL
The following works have been completed:
- Concreting of the permanent lining.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station.
The following works are put on hold:
- Installation of doors at E/M level.
The following works are in progress:
- Cleaning works
- Cement mortar laying works at the ticketing level
- Installation of floor granite slabs at the platform level
- Installation of floor tiles in the personnel areas (ticketing level)
- Preparatory works for painting at staircases 7 and 8
- Conservation of the archaeological finds of the Project.
UNDERGROUND PART OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, walls and platform slab.
The following works are in progress:
- Cement mortar laying works at the platform level.
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and works related to secondary concreting.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concrete.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Waterproofing of the permanent lining
The following works are put on hold:
- Backfilling – compaction related works.
The following works are in progress:
- Secondary concrete at the access gallery.
DELIGIANNI SHAFT
The following works have been completed:
- Excavation and temporary retaining up to the final level
- Waterproofing, construction of foundation slab and perimeter walls down to -3.0.
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works have been completed:
- Excavation – temporary retaining
- Concreting of the foundation of the shaft’s permanent lining
- Concreting of the permanent lining of the connecting tunnel.