TZAVELA SHAFT
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
The following works are in progress:
- Masonry walls.
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Completion of the permanent lining of the shaft.
The following works are in progress:
- Waterproofing of the roof slab.
- Masonry walls – plastering works at levels -4, -3, -2 and -1.
- Architectural finishes – Painting works at levels -4, -3
- Industrial flooring at levels -4, -3 and -2.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Permanent lining of the station’s main tunnel.
The following works are in progress:
- Secondary concreting in platforms.
UNDERGROUND NATM SECTIONS OF THE STATION (NATM)
The following works have been completed:
- Completion of excavation works and temporary retaining of the east elevator.
- Completion of construction of the permanent lining of the east elevator of the station.
MELA SHAFT
The following works have been completed:
- Waterproofing of the NATM connecting tunnel.
- Concreting of the final lining of the NATM tunnel (vault + reverse arch).
The following works are in progress:
- Concreting of the foundation slab (pumping station) and of the perimeter walls.
PIRAEUS STATION
The following works have been completed:
- Waterproofing of the main station.
- Concreting of the main station.
- Removal of all struts.
The following works are in progress:
- Construction of architectural finishes (masonry walls, plastering, painting works, floor filling, industrial flooring).
- Installation of formwork, reinforcement and concreting of interior staircases.
- Excavation and temporary retaining of access 1.
- Excavation of entrance 2.
- Installation of waterproofing at the roof slab.
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Construction of permanent lining.
The following works are in progress:
- Concreting of the shaft’s roof slab (completed).
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station.
The following works are put on hold:
- Installation of doors at E/M level.
The following works are in progress:
- Cleaning works.
- Cement mortar laying works at the ticketing level and the E/M floor.
- Installation of floor granite slabs at the platform level.
- Installation of floor and wall tiles in the personnel areas (ticketing level).
- Painting preparatory works at staircases 7 and 8.
UNDERGROUND SECTION OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, walls and platform slab.
The following works are in progress:
- Installation of floor granites.
DIMOTIKO THEATRO VENTILATION SHAFT
The following works have been completed:
- Concreting of the permanent lining.
RALLIOS SHAFT VENTILLATION TUNNEL
The following works have been completed:
- Concreting of the permanent lining
The following works are in progress:
Repairs to concreting works and application of polyurethane.