TZAVELA SHAFT
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Completion of the permanent lining of the shaft.
The following works are in progress:
- Waterproofing of the roof slab.
- Masonry walls – plastering works at levels -4, -3, -2 and -1.
- Architectural finishes – Painting works at levels -4, -3, -2, -1.
- Industrial flooring at levels -4, -3, -2, -1.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Permanent lining of the station’s main tunnel.
The following works are in progress:
- Secondary concreting in platforms.
SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
- Masonry walls – plastering works.
The following works are in progress:
- Surface reinstatement works.
- Construction of perimeter wall at the expropriation boundaries.
NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
The following works are in progress:
- Pile cap beam demolition.
MELA SHAFT
The following works have been completed:
- Concreting of the final lining of the NATM tunnel (vault + reverse arch).
- Concreting of the foundation slab.
The following works are in progress:
- Installation of reinforcement and concreting of the perimeter walls and the roof slab of the shaft’s pumping station.
PIRAEUS STATION
The following works have been completed:
- Concreting of the main station
The following works are in progress:
- Excavation and temporary retaining of entrance 1.
- Excavation and temporary retaining of entrance 2.
- Construction of architectural finishes (masonry walls, plastering, painting works, industrial flooring, floor filling, installation of tiles at level -3, filling works at level -2, steel doors).
- Installation of formwork, reinforcement and concreting of interior staircases.
- High pressure water blasting at the diaphragm walls between the station and entrance 1 at the concourse level (-1).
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Construction of permanent lining.
The following works are in progress:
- Removal of scaffoldings.
- Concrete repair works.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station.
The following works are put on hold:
- Installation of doors at E/M level.
The following works are in progress:
- Cleaning works.
- Backfilling – compaction works at street level.
- Installation of doors at the E/M floor.
- Installation of floor and wall tiles in the personnel areas (ticketing level).
- Painting works at the concourse level.
- Installation of floor granite slabs at the platform level.
- Painting preparatory works at staircases 7 and 8.
- Conservation of the Project’s archaeological finds.
UNDERGROUND SECTION OF THE STATION
The following works have been completed:
- Concreting of the permanent lining, walls and platform slab.
The following works are in progress:
- Installation of floor granites.
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and secondary concrete.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concrete.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining.
The following works are put on hold:
- Backfilling – compaction related works
The following works are in progress:
- Construction of support system for wall-mounted granites in the access gallery
- Preparation works for secondary concrete in the area where the pebbled floor is exhibited.
DIMOTIKO THEATRO VENTILATION SHAFT
The following works have been completed:
- Concreting of the permanent lining.
The following works are in progress:
- Pile cap beam demolition at street level.
- Backfilling – compaction related works.
- Painting works at the shaft.
RALLIOS SHAFT VENTILLATION TUNNEL
The following works have been completed:
- Concreting of the permanent lining.
TRIPLE TRACK NATM TUNNEL
The following works have been completed:
- Concreting of the permanent lining.
DELIGIANNI SHAFT
The following works have been completed:
- Excavation and temporary retaining up to the final level
- Waterproofing, construction of foundation slab and perimeter walls down to -3.0.
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works have been completed:
- Concreting of the foundation of the shaft’s permanent lining
- Concreting of the permanent lining of the connecting tunnel.
The following works are in progress:
- Concreting of the shaft’s perimeter walls (completed down
- to -4.5)