TZAVELLA SHAFT
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
- Construction of sound absorbing plaster.
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Completion of the permanent lining of the shaft.
The following works are in progress:
- Waterproofing of the roof slab.
- Construction of shafts No. 4 and 8 at street level.
- Masonry walls – plastering works at levels -4, -3, -2 and -1.
- Architectural finishes – Painting works at levels -4, -3, -2, -1.
- Industrial flooring at levels -4, -3, -2, -1.
- Installation of ceramic tiles and granites at levels -4, -3, -2, -1.
- Installation of metal structures in room 3.12.
- Installation of doors.
- Installation of ventilation grids.
- Station backfilling.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Completion of the permanent lining of the station’s main tunnel.
- Secondary concreting in platforms.
- Installation of granites in platforms.
The following works are in progress:
- Installation of false ceilings and side-covering panels.
UNDERGROUND NATM SECTIONS OF THE STATION (NATM)
The following works have been completed:
- Completion of the construction of the permanent lining.
The following works are in progress:
- Installation of granites at the entrances of the staircases and at the cross-over tunnel.
- Installation of items supporting the platforms’ metal lining at the upper transverse access tunnel.
SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
- Masonry walls – plastering works.
- Construction of perimeter wall at the boundaries of the expropriation.
- Construction of metal structures at K.P. +8.36 and +21.00.
The following works are in progress:
- Secondary staircase concreting works.
- Architectural finishes (painting works).
NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
- Pile cap beam demolition.
- Installation of metal structures at K.P. +8.08 and +24.98.
- Construction of sound absorbing plaster.
The following works are in progress:
- Architectural finishes (painting works).
MELA SHAFT
The following works have been completed:
- Concreting of the final lining of the NATM tunnel (vault + reverse arch).
- Concreting of the pumping station roof
The following works are in progress:
- Installation of reinforcement and concreting of the perimeter walls of the permanent lining.
PIRAEUS STATION
The following works have been completed:
- Concreting of main station.
The following works are in progress:
- Excavation and temporary retaining of entrances 1, 2 & 3.
- Construction of architectural finishes (masonry walls, plastering at level -1, painting works at levels -1 and -3, industrial flooring, floor filling, floor screed concrete works, installation of ceramic tiles at levels -1 and -2, metal doors at levels -2 and -3, filling laying works at levels -1 and -2, false-ceilings), area configuration works at ticketing level -1).
- Laying of electrical insulation sheets at platform level.
- Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.
- Hydro-demolition of diaphragm walls between the station and the accesses 1 and 2 at levels -1 and -2.
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Sealing of the temporary pumping station.
The following works are in progress:
- Reinstatement works at street level.
- Water proofing works at the roof of the shaft
- Laying of industrial flooring.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station
The following works are in progress:
- Construction of routing of E/M networks at street level
- Backfilling – compaction works
- Installation of doors at the platform the E/M levels
- Installation of floor granite at the ticketing level and at the staircases
- Conservation of the Project’s archaeological finds.
UNDERGROUND SECTION OF THE STATION
The following works have been completed:
- Concreting of the permanent lining
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and secondary concrete.
The following works are in progress:
- Installation of floor granite at the staircases.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concrete.
The following works are in progress:
- Installation of floor granite at the connecting tunne.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining
The following works are in progress:
- Installation of floor granite at the connecting tunnel
DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY
The following works have been completed:
- Sealing of the temporary pumping station
The following works are in progress:
- Reinstatement at street level
TRIPLE TRACK NATM TUNNEL
The following works have been completed:
- Construction of permanent lining
DELIGIANNI SHAFT
The following works have been completed:
- Excavation and temporary retaining
- Waterproofing, construction of foundation slab and perimeter walls down to -3.0.
The following works are in progress:
- Waterproofing of perimeter walls up to +8.5
- Concreting of slab down to -2.52 (completed)
- Concreting of perimeter walls up to +2.5
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works have been completed:
- Concreting of the permanent lining of the connecting tunnel.
The following works are in progress:
- Concreting of permanent lining of the shaft’s perimeter walls (completed up to +19.5)