Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Πειραιάς ιούνιος 2021

TZAVELLA SHAFT

 The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Construction of sound absorbing plaster.

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Completion of the permanent lining of the shaft.

The following works are in progress:

  • Waterproofing of the roof slab.
  • Construction of shafts No. 4 and 8 at street level.
  • Masonry walls – plastering works at levels -4, -3, -2 and -1.
  • Architectural finishes – Painting works at levels -4, -3, -2, -1.
  • Industrial flooring at levels -4, -3, -2, -1.
  • Installation of ceramic tiles and granites at levels -4, -3, -2, -1.
  • Installation of metal structures in room 3.12.
  • Installation of doors.
  • Installation of ventilation grids.
  • Station backfilling.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

 The following works have been completed:

  • Completion of the permanent lining of the station’s main tunnel.
  • Secondary concreting in platforms.
  • Installation of granites in platforms.

The following works are in progress:

  • Installation of false ceilings and side-covering panels.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Completion of the construction of the permanent lining.

The following works are in progress:

  • Installation of granites at the entrances of the staircases and at the cross-over tunnel.
  • Installation of items supporting the platforms’ metal lining at the upper transverse access tunnel.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Masonry walls – plastering works.
  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.

The following works are in progress:

  • Secondary staircase concreting works.
  • Architectural finishes (painting works).

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Completion of the permanent lining of the shaft and of the connecting tunnel.
  • Pile cap beam demolition.
  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.

The following works are in progress:

  • Architectural finishes (painting works).

MELA SHAFT

The following works have been completed:

  • Concreting of the final lining of the NATM tunnel (vault + reverse arch).
  • Concreting of the pumping station roof

The following works are in progress:

  • Installation of reinforcement and concreting of the perimeter walls of the permanent lining.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station.

The following works are in progress:

  • Excavation and temporary retaining of entrances 1, 2 & 3.
  • Construction of architectural finishes (masonry walls, plastering at level -1, painting works at levels -1 and -3, industrial flooring, floor filling, floor screed concrete works, installation of ceramic tiles at levels -1 and -2, metal doors at levels -2 and -3, filling laying works at levels -1 and -2, false-ceilings), area configuration works at ticketing level -1).
  • Laying of electrical insulation sheets at platform level.
  • Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.
  • Hydro-demolition of diaphragm walls between the station and the accesses 1 and 2 at levels -1 and -2.

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.

The following works are in progress:

  • Reinstatement works at street level.
  • Water proofing works at the roof of the shaft
  • Laying of industrial flooring.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station

The following works are in progress:

  • Construction of routing of E/M networks at street level
  • Backfilling – compaction works
  • Installation of doors at the platform the E/M levels
  • Installation of floor granite at the ticketing level and at the staircases
  • Conservation of the Project’s archaeological finds.

UNDERGROUND SECTION OF THE STATION

The following works have been completed:

  • Concreting of the permanent lining

STAIRCASE GALLERIES

The following works have been completed:

  • Concreting of the permanent lining and secondary concrete.

The following works are in progress:

  • Installation of floor granite at the staircases.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining, secondary concrete.

The following works are in progress:

  • Installation of floor granite at the connecting tunne.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Concreting of the permanent lining     

The following works are in progress:

  • Installation of floor granite at the connecting tunnel

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY

The following works have been completed:

  • Sealing of the temporary pumping station

 The following works are in progress:

  • Reinstatement at street level

TRIPLE TRACK NATM TUNNEL

The following works have been completed:

  • Construction of permanent lining

DELIGIANNI SHAFT

The following works have been completed:

  • Excavation and temporary retaining
  • Waterproofing, construction of foundation slab and perimeter walls down to -3.0.

The following works are in progress:

  • Waterproofing of perimeter walls up to +8.5
  • Concreting of slab down to -2.52 (completed)
  • Concreting of perimeter walls up to +2.5

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works have been completed:

  • Concreting of the permanent lining of the connecting tunnel.

The following works are in progress:

  • Concreting of permanent lining of the shaft’s perimeter walls (completed up to +19.5)
WCAG