Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Καλαμαριά Ιούνιος 2021
  • NOMARCHIA Station (Station & Cross Over): At the cross-over, concreting works at the intermediate slab for closing of the opening are in progress.
  • ARETSOU Station: Surface reinstatement works are in progress.
  • MICRA Station (Station & Cross Overs): In the area of the 2nd cross-sections, in progress are surface reinstatement works and works for the installation of the fire-fighting system.

TRACK WORK

In progress are works for the installation of the fire-fighting system in the area of the Forestation and cabling works for the lighting system at the 4th interstation, track 1.

WCAG