TZAVELA Shaft
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
- Construction of sound absorbing plaster.
- Traffic Arrangement – Phase B’
The following works are in progress:
- Reinstatement works at Tzavela and Lakonias Streets.
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Completion of the permanent lining of the shaft.
The following works are in progress:
- Waterproofing of the roof slab.
- Masonry walls – plastering works at levels -4, -3, -2 and -1.
- Architectural finishes – Painting works at levels -4, -3, -2, -1.
- Industrial flooring at levels -4, -3, -2, -1.
- Installation of ceramic tiles and granites at levels -4, -3, -2, -1.
- Installation of metal structures in room 3.12.
- Installation of doors.
- Installation of ventilation grids.
- Station backfilling.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Completion of the permanent lining of the station’s main tunnel.
- Secondary concreting in platforms.
- Installation of granites in platforms.
The following works are in progress:
- Installation of false ceilings and side-covering panels.
UNDERGROUND NATM SECTIONS OF THE STATION (NATM)
The following works have been completed:
- Completion of the construction of the permanent lining.
The following works are in progress:
- Installation of granites at the entrances of the staircases and at the cross-over tunnel.
- Installation of items supporting metal lining at the platforms, at the station’s access galleris and at the upper transverse access tunnel.
- Installation of consolidated emergency units.
SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
- Masonry walls – plastering works.
- Construction of perimeter wall at the boundaries of the expropriation.
- Construction of metal structures at K.P. +8.36 and +21.00.
- Staircase secondary concreting works.
The following works are in progress:
- Architectural finishes (painting works).
NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)
The following works have been completed:
- Completion of the permanent lining of the shaft and of the connecting tunnel.
- Pile cap beam demolition.
- Installation of metal structures at K.P. +8.08 and +24.98.
- Construction of sound absorbing plaster.
The following works are in progress:
- Architectural finishes (painting works).
MELA SHAFT
The following works have been completed:
- Concreting of the final lining of the NATM tunnel (vault + reverse arch).
- Concreting of the pumping station roof
- Installation of reinforcement and concreting of perimeter walls.
The following works are in progress:
- Installation of reinforcement and concreting of the shaft’s staircase.
PIRAEUS STATION
The following works have been completed:
- Concreting of main station.
The following works are in progress:
- Excavation and temporary retaining of entrances 1 & 2.
- Construction of architectural finishes (painting works at levels -1 and -2 and installation of metal doors at levels -1, -2 and -3).
- Installation of mechanical equipment at levels -1, -2 and at the level underneath the platforms.
- Hydro-demolition of diaphragm walls between the station and the accesses.
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Sealing of the temporary pumping station.
The following works are in progress:
- Painting works of the shaft.
- Reinstatement at street level.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station
The following works are in progress:
- Construction of routing of E/M networks at street level
- Reinstatement at street level (flooring works using porphyry (V. Georgiou Street).
- Installation of doors at the platform the E/M levels
- Installation of floor granite at the ticketing level
- Installation of floor tiles at the platform the E/M levels
- Installation of panels at the rail-track level
- Conservation of the Project’s archaeological finds.
UNDERGROUND SECTION OF THE STATION
The following works have been completed:
- Concreting of the permanent lining
STAIRCASE GALLERIES
The following works have been completed:
- Concreting of the permanent lining and secondary concrete.
The following works are in progress:
- Installation of floor granite at the staircases.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining, secondary concrete.
The following works are in progress:
- Installation of wall
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Concreting of the permanent lining
The following works are in progress:
- Installation of floor granite at the staircase
- Reinstatement at street level (the concreting of the sub-base for cube stoned paving)
DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY
The following works have been completed:
- Sealing of the temporary pumping station
The following works are in progress:
- Painting works at the staircase
TRIPLE TRACK NATM TUNNEL
The following works have been completed:
- Construction of permanent lining
DELIGIANNI SHAFT
The following works have been completed:
- Excavation and temporary retaining
- Waterproofing, construction of foundation slab and perimeter walls down to -3.0
- Concreting of slab up to +3.00.
The following works are in progress:
- Waterproofing of perimeter walls up to +8.5
- Concreting of perimeter walls up to +7.5
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works have been completed:
- Concreting of the permanent lining of the connecting tunnel.
The following works are in progress:
- Concreting of permanent lining of the shaft’s perimeter walls (completed up to +21.3)