- NOMARCHIA Station (Station & Crossover): Street-level reinstatement works, works for the installation of stainless steel balustrades and handrails at the entrance staircase and works for the installation of lighting fixtures are in progress. At the crossover, concreting works of the roof slab for closing of the opening and waterproofing works are in progress.
- KALAMARIA Station: Preliminary works for the implementation of the 10th traffic arrangement and works for the installation of lighting fixtures and tray earthing installation works are in progress
- ARETSOU Station: Surface reinstatement works, works for the installation of stainless steel balustrades and handrails and works for the installation of the fire-fighting system are in progress.
TRACKWORK
In progress are works for the installation of the fire-fighting system at the 3rd and 5th interstations of track 1 and in the area of the Forestation. In addition, works for the installation of electrical trays and tray earthing installation works at the 2nd and 3rd interstation, tracks 1 and 2 are in progress.