TZAVELA Shaft
The following works have been completed:
- Architectural finishes – Painting works at the staircase (walls, floors).
- Construction of sound absorbing plaster.
- Installation of staircase balustrades and balustrades at the street-level staircase.
- Installation of the entrance hatch at street level.
- Reinstatement of Tzavela and Lakonias Streets, opening to the
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Construction of partition walls at the station’s expropriation limits (street level).
- Surface reinstatement (construction of road pavement and sidewalk at Mavromichali Street).
- Installation of glass panels at levels -1, -2.
- Door painting works.
- Installation of lifts at street level and at level -2.
- Installation of lighting poles at the sidewalk of Etolikou Street.
- Reinstatement of road pavement in Mavromichali Street at the west of the station.
The following works are in progress:
- Architectural finishes – Painting works at walls at levels -4, -3, -2, -1, reinstatement of concrete surfaces, preparation works for the painting of parapet walls at street level.
- Installation of false ceilings and steel cladding (panels) on the walls of the main areas at the station’s level -1.
- Construction of flower beds’ walls, slab paving works and installation of paving stones and lighting at street level.
- Laying of planting soil at the station’s flower beds.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Steel cladding on the roof and.
- Installation of information boards and signage at the platforms.
- Installation of seats at the platforms.
UNDERGROUND NATM SECTIONS OF THE STATION (NATM)
The following works have been completed:
- Installation of granites and stainless ducts (gutters).
- Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.
The following works are in progress:
- Installation of steel lining at the upper transverse access gallery.
- Installation of glass panes in lifts.
SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)
The following works have been completed:
- Construction of perimeter wall at the boundaries of the expropriation.
- Construction of metal structures at K.P. +8.36 and +21.00.
- Construction of sound absorbing plaster.
- Installation of staircase balustrades – handrails.
- Architectural finishes (painting works).
- Door painting works.
- Installation of access hatch at the street level.
- Road surface reinstatement at Koumoundourou Street, installation of lighting bollards.
The following works are in progress:
- Surface reinstatement (surrounding area).
NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)
The following works have been completed:
- Installation of metal structures at K.P. +8.08 and +24.98.
- Construction of sound absorbing plaster.
- Architectural finishes (painting works).
- Door painting works.
- Installation of staircase balustrades – handrails.
- Installation of the entrance hatch at street level.
- Construction of perimeter wall at the boundary of the expropriation.
- Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards.
The following works are in progress:
- Surface reinstatement (construction of sidewalk and of surrounding area).
MELA SHAFT
The following works have been completed:
- Concreting of pit.
The following works are in progress:
- Construction of rainwater network.
- Construction of the sidewalk of P. Mela Street.
PIRAEUS STATION
The following works have been completed:
- Concreting of main station.
The following works are in progress:
- Construction of architectural finishes (installation of glass panes at the ticketing level (-1), filling works at level -1, installation of granites at levels -1 and -3, construction of masonry and plastering works in access 3 at level -1, installation of false ceiling at level -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, wall and column cladding works at level -3 and side coverings at the public staircases, installation of handrails and balustrades at the staircases), works in the LAS, RS areas.
- Works for the extension of the sidewalk in Akti Kallimassioti.
- Electromechanical works at levels -1 and -2 and installation of air exhaust duct at the platforms’ level (-3).
- Waterproofing of access 3 at the roof slab, of the lift and the access 3 tunnel.
- Concreting of exterior and interior parapet walls, roof slab, staircase, lift and tunnel walls and parapet walls at street level in access 3.
- Concreting works at the lift of access1 and at the connecting tunnel.
- Demolition of pile cap beam adjacent to accesses 1 and 2.
- Works for the construction of rainwater network.
- Backfilling works for bringing back the street above station level.
- Removal of struts in access 3.
- Installation of ILPAP poles.
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Sealing of the temporary pumping station.
- Installation of emergency exit hatch at street level.
The following works are in progress:
Painting of industrial floor at the connecting tunnel and at the floor of the shaft..
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station.
- Traffic reinstatement at V. Georgiou Street.
- Traffic reinstatement at Karaiskou Street.
The following works are in progress:
- Reinstatement at street level (construction of inner parapet walls at the square, marble cladding works in the square, backfilling works in the flower beds, construction of water fountains).
- Installation of false ceiling at the ticketing level.
- Installation of floor granites at the mechanical floor, at the ticketing level and at the platform level.
- Painting of the floor at staircase no. 7.
- Construction of card issuing machine bases at the ticketing level.
- Painting works in areas 2.1, 2.2, 2.7, 1.8.2 of the ticketing level.
- Construction of fire-rated glass panes at platform level.
- Installation of wall panels at the platform level.
- Installation of wall-mounted granites at the platform level.
- Installation of stainless steel cladding at platform level.
- Painting works in platform fronts (track level).
- Conservation of the Project’s archaeological finds.
STAIRCASE GALLERIES
The following works are in progress:
- Installation of supports and wall and ceiling panels.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Construction of lift housing structure at street level.
The following works are in progress:
- Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.
- Implementation of the design for the display of the archaeological finds.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works are in progress:
- Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.
- Installation of the floor glass panes in the antiquities recess.
DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY
The following works have been completed:
- Sealing of the temporary pumping station.
- Sidewalk traffic reinstatement on V. Georgiou Street.
TRIPLE TRACK NATM TUNNEL
Works have been completed.
DELIGIANNI SHAFT
The following works have been completed:
- Disassembly of building crane.
The following works are pending:
- Demolition of pile cap beam.
The following works are in progress:
- Construction of inner parapet walls at the square.
- Backfilling-compaction works.
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works are in progress:
- Demolition of concrete at surface level.
- Polyurethane injections at the connecting tunnel and the shaft.
- Disassembly of building crane.
- Installation of balustrades at the staircase.
- Excavation works on Deligianni Street for the connection of the shaft with the sewage network.