TZAVELA Shaft

The following works have been completed:

  • Architectural finishes – Painting works at the staircase (walls, floors).
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades and balustrades at the street-level staircase.
  • Installation of the entrance hatch at street level.
  • Reinstatement of Tzavela and Lakonias Streets, opening to the

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Construction of partition walls at the station’s expropriation limits (street level).
  • Surface reinstatement (construction of road pavement and sidewalk at Mavromichali Street).
  • Installation of glass panels at levels -1, -2.
  • Door painting works.
  • Installation of lifts at street level and at level -2.
  • Installation of lighting poles at the sidewalk of Etolikou Street.
  • Reinstatement of road pavement in Mavromichali Street at the west of the station.

 The following works are in progress:

  • Architectural finishes – Painting works at walls at levels -4, -3, -2, -1, reinstatement of concrete surfaces, preparation works for the painting of parapet walls at street level.
  • Installation of false ceilings and steel cladding (panels) on the walls of the main areas at the station’s level -1.
  • Construction of flower beds’ walls, slab paving works and installation of paving stones and lighting at street level.
  • Laying of planting soil at the station’s flower beds.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Steel cladding on the roof and.
  • Installation of information boards and signage at the platforms.
  • Installation of seats at the platforms.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Installation of granites and stainless ducts (gutters).
  • Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.

The following works are in progress:

  • Installation of steel lining at the upper transverse access gallery.
  • Installation of glass panes in lifts.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades – handrails.
  • Architectural finishes (painting works).
  • Door painting works.
  • Installation of access hatch at the street level.
  • Road surface reinstatement at Koumoundourou Street, installation of lighting bollards.

The following works are in progress:

  • Surface reinstatement (surrounding area).

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (painting works).
  • Door painting works.
  • Installation of staircase balustrades – handrails.
  • Installation of the entrance hatch at street level.
  • Construction of perimeter wall at the boundary of the expropriation.
  • Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards.

The following works are in progress:

  • Surface reinstatement (construction of sidewalk and of surrounding area).

MELA SHAFT

The following works have been completed:

  • Concreting of pit.

The following works are in progress:

  • Construction of rainwater network.
  • Construction of the sidewalk of P. Mela Street.

PIRAEUS STATION

The following works have been completed:

  • Concreting of main station.

The following works are in progress:

  • Construction of architectural finishes (installation of glass panes at the ticketing level (-1), filling works at level -1, installation of granites at levels -1 and -3, construction of masonry and plastering works in access 3 at level -1, installation of false ceiling at level -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, wall and column cladding works at level -3 and side coverings at the public staircases, installation of handrails and balustrades at the staircases), works in the LAS, RS areas.
  • Works for the extension of the sidewalk in Akti Kallimassioti.
  • Electromechanical works at levels -1 and -2 and installation of air exhaust duct at the platforms’ level (-3).
  • Waterproofing of access 3 at the roof slab, of the lift and the access 3 tunnel.
  • Concreting of exterior and interior parapet walls, roof slab, staircase, lift and tunnel walls and parapet walls at street level in access 3.
  • Concreting works at the lift of access1 and at the connecting tunnel.
  • Demolition of pile cap beam adjacent to accesses 1 and 2.
  • Works for the construction of rainwater network.
  • Backfilling works for bringing back the street above station level.
  • Removal of struts in access 3.
  • Installation of ILPAP poles.

ROLOI SHAFT & NATM ACCESS TUNNEL

 The following works have been completed:

  • Sealing of the temporary pumping station.
  • Installation of emergency exit hatch at street level.

The following works are in progress:

Painting of industrial floor at the connecting tunnel and at the floor of the shaft..

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Sealing of the temporary pumping station.
  • Traffic reinstatement at V. Georgiou Street.
  • Traffic reinstatement at Karaiskou Street.

The following works are in progress:

  • Reinstatement at street level (construction of inner parapet walls at the square, marble cladding works in the square, backfilling works in the flower beds, construction of water fountains).
  • Installation of false ceiling at the ticketing level.
  • Installation of floor granites at the mechanical floor, at the ticketing level and at the platform level.
  • Painting of the floor at staircase no. 7.
  • Construction of card issuing machine bases at the ticketing level.
  • Painting works in areas 2.1, 2.2, 2.7, 1.8.2 of the ticketing level.
  • Construction of fire-rated glass panes at platform level.
  • Installation of wall panels at the platform level.
  • Installation of wall-mounted granites at the platform level.
  • Installation of stainless steel cladding at platform level.
  • Painting works in platform fronts (track level).
  • Conservation of the Project’s archaeological finds.

STAIRCASE GALLERIES

The following works are in progress:

  • Installation of supports and wall and ceiling panels.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Construction of lift housing structure at street level.

The following works are in progress:

  • Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.
  • Implementation of the design for the display of the archaeological finds.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works are in progress:

  • Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.
  • Installation of the floor glass panes in the antiquities recess.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY 

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk traffic reinstatement on V. Georgiou Street.

 TRIPLE TRACK NATM TUNNEL

Works have been completed.

DELIGIANNI SHAFT

The following works have been completed:

  • Disassembly of building crane.

The following works are pending:

  • Demolition of pile cap beam.

The following works are in progress:

  • Construction of inner parapet walls at the square.
  • Backfilling-compaction works.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works are in progress:

  • Demolition of concrete at surface level.
  • Polyurethane injections at the connecting tunnel and the shaft.
  • Disassembly of building crane.
  • Installation of balustrades at the staircase.
  • Excavation works on Deligianni Street for the connection of the shaft with the sewage network.