TZAVELA Shaft
The following works have been completed:
- Architectural finishes – Painting works at the staircase (walls, floors).
- Construction of sound absorbing plaster.
- Installation of staircase balustrades and balustrades at the street-level staircase.
- Installation of the entrance hatch at street level.
- Reinstatement of Tzavela and Lakonias Streets, opening to the
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Construction of partition walls at the station’s expropriation limits (street level).
- Surface reinstatement (construction of road pavement and sidewalk at Mavromichali Street).
- Installation of glass panels at levels -1, -2.
- Door painting works.
- Installation of lifts at street level and at level -2.
- Installation of lighting poles at the sidewalk of Etolikou Street.
- Reinstatement of road pavement in Mavromichali Street at the west of the station.
The following works are in progress:
- Architectural finishes – Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level.
- Installation of steel cladding (panels) on the walls and of metal side covers at the station’s escalators.
- Slab paving works and installation of paving stones and lighting at street level.
- Laying of planting soil at the station’s flower beds.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Steel cladding on the roof and side covers.
- Installation of information boards and signage at the platforms.
- Installation of seats at the platforms.
- Installation of radio communication (TETRA) cable.
UNDERGROUND NATM SECTIONS OF THE STATION (NATM)
The following works have been completed:
- Installation of granites and stainless ducts (gutters).
- Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.
- Installation of lifts glass panes.
The following works are in progress:
- Installation of metal side covers and handrails at the station’s escalators.
SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)
The following works have been completed:
- Construction of perimeter wall at the boundaries of the expropriation.
- Construction of metal structures at K.P. +8.36 and +21.00.
- Construction of sound absorbing plaster.
- Installation of staircase balustrades – handrails.
- Architectural finishes (re-painting works).
- Door painting works.
- Installation of access hatch at the street level.
- Road surface reinstatement at Koumoundourou Street, installation of lighting bollards.
The following works are in progress:
- Surface reinstatement (surrounding area).
NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)
The following works have been completed:
- Installation of metal structures at K.P. +8.08 and +24.98.
- Construction of sound absorbing plaster.
- Architectural finishes (re-painting works).
- Door painting works.
- Installation of staircase balustrades – handrails.
- Installation of the entrance hatch at street level.
- Construction of perimeter parapet walls at the boundary of the expropriation.
- Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards.
The following works are in progress:
- Surface reinstatement (construction of sidewalk and of surrounding area).
MELA SHAFT
The following works have been completed:
- Concreting of pit.
The following works are in progress:
- Installation of hydraulic emergency exit door.
PIRAEUS STATION
The following works have been completed:
- Concreting of main station.
The following works are in progress:
- Construction of architectural finishes (filling works at level -1, installation of granites at levels -1 and -3, installation of false ceiling at levels -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, wall and column cladding works at level -3 and side coverings at the public staircases, installation of handrails and balustrades at the staircases), works in the LAS, RS areas.
- Electromechanical works at levels -1 and -2 and installation of air exhaust duct at the platforms’ level (-3).
- Waterproofing of access 3 at the roof slab, of the lift and the access 3 tunnel.
- Concreting of exterior and interior parapet walls, roof slab, staircase and of parapet walls at street level in access 3.
- Works for the construction of rainwater network.
- Backfilling works for bringing back the street above station level.
- Installation of ILPAP poles.
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Sealing of the temporary pumping station.
- Installation of emergency exit hatch at street level.
The following works are in progress:
- Painting of staircase floor.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Sealing of the temporary pumping station.
- Traffic reinstatement at V. Georgiou and Karaiskou Streets.
The following works are in progress:
- Reinstatement at street level (construction of inner parapet walls at the square, marble cladding works in the square, paving works, construction of water fountains, transfer of Venizelos statue at its initial location).
- Construction of wall-mounted granite at street level (Aghiou Konstantinou square entrance).
- Installation of false ceiling at the ticketing level (public areas and personnel rooms).
- Installation of floor granites at the mechanical floor, at the ticketing level and at the platform level.
- Painting of floors at staircases No. 7, 8, 3.12, 3.1.3 (ticketing level) and 3.1.4, 3.1.5 (platform level).
- Painting works in areas 3.19.4, 3.1.3 and 1.10.6 of the ticketing level.
- Construction of fire-rated glass panes at platform level.
- Installation of wall panels at the platform level.
- Painting works in platform fronts (track level).
- Installation of roller shutters at the main entrance.
- Conservation of the Project’s archaeological finds.
STAIRCASE GALLERIES
The following works are in progress:
- Installation of supports and wall and ceiling panels.
- Installation of handrails at the staircases.
- Installation of floor granites.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Construction of lift housing structure at street level.
The following works are in progress:
- Installation of supports for the wall and ceiling panels according to the design for the display of the archaeological finds.
- Implementation of the design for the display of the archaeological finds.
- Installation of roller shutters.
- Installation of floor granites.
- Wall-mounted granites at the staircase termination point at street level.
- Reinstatement at street level (excavation for E/M networks at the surface, backfilling-compaction, concreting of paving stone sub-base).
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works are in progress:
- Installation of wall and ceiling panels according to the design for the display of the archaeological finds.
- Installation of granite floors.
- Materialization of the design for the display of the archaeological finds in the recess.
- Installation of roller shutters.
- Construction of false ceiling at the staircase.
DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY
The following works have been completed:
- Sealing of the temporary pumping station.
- Sidewalk traffic reinstatement on V. Georgiou Street.
TRIPLE TRACK NATM TUNNEL
Works have been completed.
DELIGIANNI SHAFT
The following works have been completed:
- Disassembly of building crane.
The following works are pending:
- Demolition of pile cap beam.
The following works are in progress:
- Construction of inner parapet walls at the square.
- Backfilling-compaction works.
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works are in progress:
- Demolition of concrete at surface level.
- Excavation works on Deligianni Street for the connection of the shaft with the sewage network.
- Preparatory works for floor painting at the staircase.