• NOMARCHIA Station (Station and Crossover): In the station area, in progress are works for escalators setting. At the Crossover, in progress are road-paving works as well as works for the installation of protective pipes for the routing of MV cables at the PPC substation.
• ARETSOU Station: In progress are works for the installation of a network and equipment for the HVAC system, as well as works for the installation of transformer bases at the LAS and traction supply substations.
• NEA KRINI Station: In progress are works for the installation of tunnel ventilation equipment.
• MICRA Station (Station and Crossover): In progress are works for the installation of cement boards at the Ticketing level. Moreover, in progress are works for the construction of earthing of trays and cabling for the lighting network, as well as network and equipment installation works for the HVAC system
TRACKWORK: Completed are works for the construction of the turnouts/crossovers in Nomarchia Crossover area, as well as works for the installation of handrails in the tunnel, track 2.