TZAVELA Shaft
The following works have been completed:
- Architectural finishes – Painting works at the staircase (walls, floors).
- Construction of sound absorbing plaster.
- Installation of staircase balustrades and balustrades at the street level staircase.
- Installation of the entrance hatch at street level.
- Installation of roller shutters.
- Reinstatement of Tzavela and Lakonias Streets, opening to the
MANIATIKA STATION
STATION’s OPEN CUT
The following works have been completed:
- Surface reinstatement (construction of road pavement and sidewalks at Mavromichali Street).
- Installation of glass panels at levels -1, -2.
- Door painting works.
- Installation of lifts at street level and at level -2.
- Installation of lighting poles at the sidewalk of Etolikou Street.
- Reinstatement of road pavement in Mavromichali Street at the west of the station.
The following works are in progress:
- Architectural finishes – Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level.
- Installation of steel cladding (panels) on the walls/ceilings and of metal side covers at the station’s escalators.
- Installation of stainless steel handrails.
- Installation of the station’s signage.
- Construction of partition walls at the station’s south expropriation limits (street level)
- Surface reinstatement (construction of road pavement and sidewalks at Etolikou Street)
- Slab paving works and installation of paving stones and lighting at street level.
- Laying of planting soil at the station’s flower beds.
- Connection of the station with EYDAP network.
MAIN TUNNEL OF THE STATION (ΝΑΤΜ)
The following works have been completed:
- Steel cladding on the roof and side covers.
- Installation of information boards and signage at the platforms.
- Installation of seats at the platforms.
- Installation of radio communication (TETRA) cable.
UNDERGROUND NATM SECTIONS OF THE STATION (NATM)
The following works have been completed:
- Installation of granites and stainless ducts (gutters).
- Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.
- Installation of lifts glass panes.
- Installation of metal side covers and handrails at the station’s escalators.
SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)
The following works have been completed:
- Construction of perimeter wall at the boundaries of the expropriation.
- Construction of metal structures at K.P. +8.36 and +21.00.
- Construction of sound absorbing plaster.
- Installation of staircase balustrades – handrails.
- Architectural finishes (re-painting works).
- Door painting works.
- Installation of access hatch at the street level.
- Road surface reinstatement at Koumoundourou Street, installation of lighting bollards.
NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)
The following works have been completed:
- Installation of metal structures at K.P. +8.08 and +24.98.
- Construction of sound absorbing plaster.
- Architectural finishes (re-painting works).
- Door painting works.
- Installation of staircase balustrades – handrails.
- Installation of the entrance hatch at street level.
- Construction of perimeter parapet walls at the boundary of the expropriation.
- Road surface reinstatement at Dimitrakopoulou Street, installation of lighting bollards.
MELA SHAFT
The following works have been completed:
- Concreting of pit.
PIRAEUS STATION
The following works have been completed:
- Concreting of main station.
The following works are in progress:
- Construction of architectural finishes (filling works, installation of granites at levels -1 and -3, installation of false ceiling at levels -1 and -3, painting works at levels -1 and -2, at the staircases and at track level, installation of glass panes at level -1, wall and column cladding works at level -3 and side coverings at the public staircases, painting of doors and installation of their accessories, works in the LAS, RS areas.
- Electromechanical works at levels -1 and -2.
- Installation of granites and marbles at street level.
- Installation of gutters, curbs and construction of sidewalks inside and outside the main worksite area and installation of ILPAP columns.
- Installation of shaft grids.
- Works for the construction of the asphalt sub-base to bring back the street above station level.
- Network reinstatement works at street level (PPC, OTE, sewage, etc.)
- Asphalt paving at the street section in front of the Suburban Railway Station.
- Works for the installation of station lifts (frame – glass panes).
- Installation of plant irrigation network and other reinstatement works at street level.
- Installation of signs at the platform and ticket issuing levels.
ROLOI SHAFT & NATM ACCESS TUNNEL
The following works have been completed:
- Sealing of the temporary pumping station.
- Installation of emergency exit hatch at street level.
DIMOTIKO THEATRO STATION
MAIN STATION – AGHIOU KONSTANTINOU SQUARE
The following works have been completed:
- Opening of V. Georgiou and Karaiskou Streets to the traffic.
The following works are in progress:
- Reinstatement at street level.
- Painting of the floor of the mechanical level.
- Installation of false ceiling at the ticketing level and at the platform level.
- Installation of floor granites at the ticketing level and at the platform level.
- Installation of glass panes at the lift pits.
- Construction of stainless cladding, stanchion and balustrades at the ticketing and at platform levels.
- Installation of ironmongery on the doors.
- Assembly-disassembly of building crane.
- Conservation of the Project’s archaeological finds.
STAIRCASE GALLERIES
The following works are in progress:
- Installation of supports and wall and ceiling panels.
- Installation of handrails at the staircases.
- Installation of floor granites.
KORAI SQUARE ENTRANCE AND ACCESS GALLERY
The following works have been completed:
- Construction of lift housing structure at street level.
The following works are in progress:
- Reinstatement at street level.
- Installation of wall and ceiling panels according to the design for the display of the archaeological finds.
- Implementation of the design for the display of the archaeological finds in the recess.
- Wall-mounted granites at the staircase termination point at street level.
BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY
The following works are in progress:
- Installation of wall and ceiling panels according to the design for the display of the archaeological finds.
- Installation of granite floors.
- Implementation of the design for the display of the archaeological finds in the recess.
DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY
The following works have been completed:
- Sealing of the temporary pumping station.
- Sidewalk traffic reinstatement on V. Georgiou Street.
The following works are in progress:
- Reinstatement at street level.
TRIPLE TRACK NATM TUNNEL
Works have been completed.
DELIGIANNI SHAFT
The following works have been completed:
- Disassembly of building crane.
The following works are in progress:
- Construction of parapet walls at the square.
- Demolition of pile cap beam.
- Backfilling-compaction works.
PANEPISTIMIO SHAFT & VENTILATION TUNNEL
The following works are in progress:
- Reinstatement at street level.
- Construction of shaft safety railing.