SEPTEMBER 2022

TZAVELA Shaft

The following works have been completed:

  • Architectural finishes – Painting works at the staircase (walls, floors).
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades and balustrades at the street level staircase.
  • Installation of the entrance hatch at street level.
  • Installation of roller shutters.
  • Reinstatement of Tzavela and Lakonias Streets, opening to the

The following works are in progress:

  • Restoration of minor deficiencies.

MANIATIKA STATION

STATION’s OPEN CUT      

The following works have been completed:

  • Surface reinstatement (construction of road pavement and sidewalks at Mavromichali Street).
  • Installation of glass panels at levels -1, -2.
  • Door painting works.
  • Installation of lifts at street level and at level -2.
  • Installation of lighting poles at the sidewalk of Etolikou Street.
  • Reinstatement of road pavement in Mavromichali Street.
  • Architectural finishes – Re-painting works at walls and floors at levels -4, -3, -2, -1, reinstatement of concrete surfaces, re-painting works of parapet walls at street level.
  • Installation of steel cladding (panels) on the walls/ceilings and of metal side covers at the station’s escalators.
  • Installation of stainless steel handrails.
  • Installation of the station’s signage.
  • Construction of partition walls at the station’s south expropriation limits (street level)
  • Surface reinstatement (construction of road pavement and sidewalks at Etolikou Street)
  • Slab paving works and installation of paving stones and lighting at street level.
  • Laying of planting soil, planting of trees, bushes and lawn at the station’s flower beds.
  • Connection of the station with EYDAP network.
  • Installation of waste bins, seats (benches), bicycle-motorcycle stands at the square.
  • Removal of worksite fences.
  • Installation of traffic signs and removal of temporary signs that had been installed due to traffic diversions.
  • Opening to the traffic of Etolikou, Koumoundourou, Dimitrakopoulou, Gythiou and Mavromichali Streets.

The following works are in progress:

  • Restoration of minor deficiencies.

MAIN TUNNEL OF THE STATION (ΝΑΤΜ)

The following works have been completed:

  • Steel cladding on the roof and side covers.
  • Installation of information boards and signage at the platforms.
  • Installation of seats at the platforms.
  • Installation of radio communication (TETRA) cable.

The following works are in progress:

  • Restoration of minor deficiencies.

UNDERGROUND NATM SECTIONS OF THE STATION (NATM)

The following works have been completed:

  • Installation of granites and stainless ducts (gutters).
  • Installation of lining (made of steel and gypsum boards) at the access tunnels of the station.
  • Installation of lifts glass panes.
  • Installation of metal side covers and handrails at the station’s escalators.

The following works are in progress:

  • Restoration of minor deficiencies.

SOUTH VENTILATION SHAFT OF THE STATION (Koumoundourou Street)

The following works have been completed:

  • Construction of perimeter wall at the boundaries of the expropriation.
  • Construction of metal structures at K.P. +8.36 and +21.00.
  • Construction of sound absorbing plaster.
  • Installation of staircase balustrades – handrails.
  • Architectural finishes (re-painting works).
  • Door painting works.
  • Installation of access hatch at the street level.
  • Road surface reinstatement, opening to traffic of Koumoundourou Street, installation of lighting bollards, waste bins and seats.

The following works are in progress:

  • Restoration of minor deficiencies.

NORTH VENTILATION SHAFT OF THE STATION (Dimitrakopoulou Street)

The following works have been completed:

  • Installation of metal structures at K.P. +8.08 and +24.98.
  • Construction of sound absorbing plaster.
  • Architectural finishes (re-painting works).
  • Door painting works.
  • Installation of staircase balustrades – handrails.
  • Installation of the entrance hatch at street level.
  • Construction of perimeter parapet walls at the boundary of the expropriation.
  • Road surface reinstatement, opening to traffic of Dimitrakopoulou Street, installation of lighting bollards, waste bins, and seats and planting of trees.

The following works are in progress:

  • Restoration of minor deficiencies.

MELA SHAFT

The following works have been completed:

  • Painting works at the staircase and the remaining areas.

The following works are in progress:

  • Still pending is the reinstatement of the square’s area that had been occupied.

PIRAEUS STATION

The following works have been completed:

  • Painting works at the station.
  • Construction of fillings and industrial floors.
  • Installation of metal doors.
  • Installation of granites.
  • Walls and columns lining.
  • Installation of false ceilings.
  • Installation of galvanized metal panels.
  • Backfilling of entrances.
  • Installation of lifts.
  • Construction of sidewalks and installation of granites and marbles at street level.
  • Construction of sub-base and asphalt laying works.
  • Planting works and installation of irrigation system.
  • Installation of trays at street level.

The following works are in progress:

  • Reinstatement of ISAP area.
  • Reinstatement of OLP area.

ROLOI SHAFT & NATM ACCESS TUNNEL

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Installation of emergency exit hatch at street level.

DIMOTIKO THEATRO STATION

MAIN STATION – AGHIOU KONSTANTINOU SQUARE

The following works have been completed:                                                                                 

  • Opening of V. Georgiou and Karaiskou Streets to the traffic.
  • Installation of false ceiling at the ticketing level and at the platform level.
  • Installation of floor granites at the ticketing level.
  • Construction of stainless cladding, stanchion and balustrades at the ticketing level, at the platform level and the staircases.
  • Installation of ironmongery on the doors.
  • Conservation of the Project’s archaeological finds.

 The following works are in progress:

  • Reinstatement at street level (slab paving works, planting works, irrigation network for planting areas etc.).
  • Painting of the floor of the mechanical level and re-painting works of the walls of the technical rooms

STAIRCASE GALLERIES

The following works are in progress:

  • Installation of supports and wall and ceiling panels.
  • Installation of handrails at the staircases.
  • Installation of floor granites.

KORAI SQUARE ENTRANCE AND ACCESS GALLERY

The following works have been completed:

  • Construction of lift housing structure at street level.
  • Removal of worksite offices from the surface level.
  • Installation of wall and ceiling panels.
  • Implementation of the design for the display of the archaeological finds in the recess.

The following works are in progress:

  • Reinstatement at street level.

BAKOYIANNI SQUARE ENTRANCE AND ACCESS GALLERY

The following works are in progress:

  • Installation of wall and ceiling panels.
  • Implementation of the design for the display of the archaeological finds in the recess.

DIMOTIKO THEATRO VENTILATION SHAFT (RALLIOS SHAFT) AND VENTILATION GALLERY     

The following works have been completed:

  • Sealing of the temporary pumping station.
  • Sidewalk traffic reinstatement on V. Georgiou Street.
  • Removal of sidewalk in the framework of the implementation of the permanent traffic study.
  • Painting of the floor of the connecting tunnel.

TRIPLE TRACK NATM TUNNEL

Works have been completed.

DELIGIANNI SHAFT

The following works have been completed:

  • Disassembly of building crane.

The following works are in progress:

  • Reinstatement at street level.

PANEPISTIMIO SHAFT & VENTILATION TUNNEL

The following works are in progress:

  • Reinstatement at street level.