Θεσσαλονίκη Οκτώβριος 2022
  • New Railway Station: In progress are greenery works in the north section of the station, works for the installation of the suspension system of the false ceilings in public areas, works for the installation of cable trays and works for the earthing of trays at level -1 and works for the installation of signaling and platform screen doors cabling.
  • DIMOKRATIAS Station: Completed are works for the marking of raised floors in the technical and personnel rooms, while in progress are works for the installation of the suspension system of the false ceilings in public areas, as well as works for the installation of signaling and traction power cabling and works for the connections with the 3rd
  • VENIZELOU Station: Completed are works for the construction of the floor slab at level -3 of the main station, as well as works for the construction of the first phase of the roof slab at the north access, works for the construction of the struts and the archaeological survey at the south-east ventilation shaft. In progress are works for the final excavation of the station, in parallel with the construction of the pre-stressed anchors for the temporary retaining of the diaphragm walls and the installation of the reinforcement of the perimeter and the inner walls between levels -2 and -3. Moreover, at completion stage are works for the implementation of traffic regulation N’ at the north section of Venizelou Station.
  • AGHIA SOPHIA Station: The archaeological excavation in the extension of the north access has been completed, while preliminary works for placing back the Krineon-Nymphaeum building are in progress. Works for the installation of sound-absorbing panels in the area of the ventilation shafts have been completed, as well as works for the installation of the mounting beams for the platform screen doors, while in progress are works for the construction of cement-mortar and industrial flooring in the technical rooms, works for the construction of a sub-base for the laying of granites in the public areas, works for the earthing of trays in the stations and the tunnels and works for the installation of the traction power equipment.
  • SINTRIVANI Station: Works for the installation of Consolidated Emergency Control Units (ECUs) at the platform level have been completed.
  • PANEPISTIMIO Station: Completed are works for the installation and the connection of the permanent compensation panels in the area of the LAS substation as well as works for the connections of the cables of the central fire detection panel. In progress are works for the reinstatement of the surrounding area in the area of the University Club of the Aristotle University of Thessaloniki, works for the construction of fire dampers and works for the closing of openings using gypsum board, works for the construction of the false ceiling suspension system at level -1 and works for the connections of the ventilation tunnels mimic panels.
  • PAPAFI Station: Completed are vertical cladding works using aluminum panels, while in progress are final painting works and cladding works using non perforated steel sheets.
  • EFKLIDIS Station: Completed are works for the construction of the shed in access 1, works for the installation of lateral steel covers for the tunnel ventilation fans and works for the installation and the connections of the lighting switchboards.
  • FLEMING Station: Completed are works for the construction of fire dampers, the installation of steel lining at the headwalls and the installation of Consolidated Emergency Control Units (ECUs) at platform levels. In progress are final painting works, works for the construction of gypsum boards and works for the installation of lateral steel covers for the tunnel ventilation fans.
  • ANALIPSI Station: Completed are street-level reinstatement works at Psychari Street, works for the installation of vertical aluminum panels in public areas and works for the installation of steel frames for the work surfaces in the ticket office. In progress are street-level reinstatement works at Drossini Street, works for the construction of the false ceiling suspension system at levels -1 and -2, works for the installation of a raised floor at the LAS substation as well as works for the installation and connections of the General Low Voltage Switchboard (GLVS).
  • 25 MARTIOU STATION: Completed are the granite cladding works of the central staircase, the installation of lighting poles of the station at street level, the construction of the elevated floor at the LAS, the installation of metal frames for work surfaces at the ticket office, as well as the installation of the general LV switchboard. In progress are the final painting works and the works for the installation of the central fire detection panel.
  • VOULGARI Station: Completed is the installation of the lighting poles of the station at street level and the installation of metal lining of the platform’s headwalls. In progress are connection works concerning the general LV switchboard.
  • NEA ELVETIA Station: Completed is the installation of the general LV switchboard and in progress are works for the construction of false ceiling made of gypsum boards in access 3, as well as works for the construction of fire dampers.

DEPOT

  • Building Complex Ι: Completed are repair works of fire resistant paints at the balcony. With regard to the electromechanical installations, in progress are works for the installation of fire detection and lighting systems.
  • Building Complex ΙΙ: With regard to the Administration and Control Centre, completed are works for the installation of frames for the wooden doors, as well as works for the installation of benches and sinks in sanitary areas at all levels. In progress are painting works, ceramic tiles cladding works, works for the installation of steel stripes on the false ceilings of the sanitary areas and the food and beverage room, works for the completion of the installation of exterior aluminum louvers, works for the installation of cabinets in the food and beverage room at all levels, as well as works for the construction of the planted terrace system. In Building 2, in progress are works for the installation of exterior lining using panels. In the surrounding area, in progress are works for the construction of networks and pits of the electromechanical system networks, works for the construction of curbs and gutters and sidewalks, and works for the construction of reinforced concrete parapet walls in the area of the eastern gate and of the new train access.

TRACKWORK:

In progress are works for the installation of the track-side signaling equipment in the tunnels between NEW RAILWAY STATION and DIMOKRATIAS Stations.