November 2022

Θεσσαλονίκη Νοέμβριος 2022
  • New Railway Station: Completed are works for the installation of the pumping stations’ discharge networks, while in progress are works for the installation of perimeter supporting angles of the raised floors in the technical rooms and the personnel areas, works for the installation of raised floor in the Station Master Room, as well as works for the installation and connection of signaling cables in the technical room cabinets.
  • DIMOKRATIAS Station: In progress are works for the construction of marble cladding at the ticketing level, the preparatory works for the installation of raised floor in the Station Master Room, as well as works for the installation of cable trays at level -1.
  • VENIZELOU Station: Completed are works for the final excavation of the station, the construction of the pre-stressed anchors for the temporary retaining of the diaphragm walls, the excavation of the south-eastern ventilation shaft, the construction of the micro-piles for the station foundation, the construction of the foundation earthing, as well as the works for the implementation of traffic arrangement N’ in the northern section of Venizelou Street. In progress are the works for the construction of the station’s invert, along with the works for the construction of the perimeter and inner walls, between levels -2 and -3.
  • AGHIA SOPHIA Station: Completed are the works for the construction of a sub-base for the laying of granites in the public areas and the lining works using granite tiles. In progress are the works for the installation of platform screen doors, the works for completing the first stage of painting activities, as well as the works for the assembly of the escalators and the installation of trays at all station’s levels.
  • SINTRIVANI Station: Completed are the works for the installation of furniture and the glass panel in the station master room, the installation of the permanent power compensation panels in the lighting and auxiliary substation, as well as the installation of the glass panel of the ticketing room. In progress are the works for the completion of the raised floors, as well as reinstatement activities at street level.
  • PANEPISTIMIO Station: Completed are works for the connection of the mimic panels of the tunnel ventilation system, as well as the connection of the feeding and supply cables, the hydraulic connections and the installation of the air-conditioning units in the personnel areas. In progress are the works and the reinstatement of the surrounding area, the construction of fire dampers and closing of openings, the works for the construction of the false ceiling at several levels and the works for the installation of the vertical cladding suspension system using aluminum panels.
  • PAPAFI Station: Completed are the works for the installation of false ceiling and cladding works using aluminum panels, the installation of the furniture in the station master room, of the handrails made of stainless steel, as well as the installation of the telecommunications equipment (cameras, loudspeakers, passenger information system, etc.). In progress are the works for the reinstatement of Papafeio Foundation and the works for the connection of the ventilation/air-conditioning system mimic panel.
  • EFKLIDIS Station: Completed are works for the installation of raised floors in the technical rooms and personnel areas, as well as works for the installation and the connections of mimic panels of the tunnel ventilation system. In progress are works for the construction of the architectural lining above the platform screen doors, works for the construction of the skylight shed at surface level and works for the installation of the mimic panel of the ventilation/air-conditioning system.
  • FLEMING Station: Completed are works for the installation of raised floors in the technical rooms and personnel areas, granite lining works in the accesses, furniture installation and works for the construction of the false-ceiling at the Station Master Room, the installation of constant power compensation panels in the Lighting and Auxiliary Substation (LAS), as well as the installation of the side steel covers of the fans of the tunnel ventilation system. In progress are works for the installation of lighting switchboards in the area of the Substation, as well as works for the completion of the facilities of the fire detection system.
  • ANALIPSI Station: Completed are the works for the installation of furniture at the Station Master Room, works for the installation of the fire-rated door frame at the ticket office and works for the installation of discharge drains of the staircases and the ventilation shafts. In progress are works for the construction of the false ceiling suspension system at levels -1, -2 and -3, works for the installation of raised floors, removable balustrades, and works for the installation of air ducts and equipment of the ventilation/ air-conditioning system.
  • 25 MARTIOU STATION: Completed are works for the installation of the false ceiling and the furniture at the Station Master Room. In progress are works for the installation of raised floors, works for the construction of false ceiling made of gypsum fiber board at the accesses, as well as works for the connections of the equipment of the ventilation/ air-conditioning system, works for the installation of the access control / intrusion detection system and works for the completion of the installation of air ducts and the ventilation/air-conditioning system and tunnel ventilation equipment.
  • VOULGARI Station: Completed is the installation of the steel desk and of the fire-rated door frame at the ticket office, while in progress are works for the installation of the suspension system of the vertical aluminum panel linings in the public areas, works for the construction of fire dampers, final painting works and works for the installation of cables.
  • NEA ELVETIA Station: Completed are vertical marble cladding works in the public areas, the installation of the steel bench and of the fire-rated door frame at the ticket office, the construction of the raised floor in the Station Master Room and the works for the construction of false ceiling made of gypsum board at the accesses. In progress are works for the construction of raised floors in the technical rooms.

DEPOT

  • Building Complex Ι: Completed are works for the construction of gypsum board partition walls above the doors of the bogie lifts, while in progress are painting works using fire-resistant paints inside the building complex. With regard to the electromechanical installations, in progress are equipment and cabling installation works of the Building Automation Control System.
  • Building Complex ΙΙ: With regard to the Administration Building and the Control Centre, completed are works for the installation of cabinets in the food and beverage rooms at all levels. In progress are works for the installation of the remaining exterior door frames and the interior aluminum glass panels, works for the installation of stainless steel food benches at all levels and works for the construction of the planted terrace system. In Building 2, in progress are works for the installation of the interior aluminum glass panels. With regard to the electromechanical works in Building Complex II, in progress are the works for the network cabling, as well as works for the construction of the fire-fighting network, works for the installation of low voltage cables, and works for the installation of the fire-detection and the access control / intrusion detection system. In the surrounding area, in progress are works for the construction of networks and pits of the electromechanical system networks, the construction of curbs, gutters and sidewalks, while completed are the works for the construction of reinforced concrete parapet walls in the area of the eastern gate and of the new train access.

TRACKWORK:

At a completion stage are works for the installation of track-side signaling equipment in the tunnels between the NEW RAILWAY Station and DIMOKRATIAS Stations.

In progress are testing and commissioning works.