- NEW RAILWAY Station: Completed are works for the installation of raised floors in technical rooms, the installation of perforated soundproof panels at track level 1 and the dismantling of the struts – first phase in the area of the forestation. In progress are works for the application of sound proof coating in the east pumping station, works for the installation of granite plugs and skirting around the openings of the slabs at the transfer level, and works for the installation of air ducts and the lighting system in the technical rooms, as well as works for the installation of low voltage systems’ cables.
- DIMOKRATIAS Station: Completed are works for the installation of raised floors in technical rooms, platform floor lining works using granite slabs, works for the installation of consolidated emergency units at the platform and the installation of a black metal sheet above the automatic platform screen doors and works for the installation of false ceiling supports at the platform level and at the transfer level. In progress are works for the installation of false ceiling supports at level -2, works for the installation of the cabling of the Building Automation Control System (BACS), works for the construction of the fire-detection system, works for the connection of lighting fixtures in track 1 and works for the installation of air ducts and tunnel ventilation equipment.
- VENIZELOU Station: Completed are works for the application of masonry wall plastering at platform level (-4) and at the electromechanical level (-3), painting works at the ceiling of track 1, as well as works for the installation of the two tracks intended for the suspension of the equipment at level -3. In progress are works for the construction of plastering at the concourse level, works for the construction of the foundation slab of the northern access, painting works at the emergency exit stairways, works for the installation of the steel beam above the automatic PSDs, works for the dismantling of the struts in the area of the south access – by means of undisturbed cut in the area of the south-east ventilation shaft – for its connection with the main station, works for the construction of the water supply system and the sewage system, works for the installation of electrical trays and works for the installation of the indoor escalators of the station. Moreover, in progress is the placing back of the archaeological finds/ unities at level -1.
- AGIAS SOFIAS Station: Completed are the remaining works for the construction of the industrial floors and works for the reinstatement of the sidewalk on Egnatias Street on the north side. In progress are works for the installation of raised floors in the technical rooms, works for the lining of floors using granite slabs at the platform and at level -2, works for the construction of vertical marble cladding at the transfer level, works for the construction of fire dampers and of the infrastructure intended for the final transportation of the traffic signaling pillars. Moreover, continued are preparatory works for the construction of the fair-faced shotcrete in the area where the antiquities are preserved in the northern access, works for the construction of the permanent drainage pit within the archaeological area of the north access, as well as works for the installation of trays and earthing, cabling of the wireless communication system.
- SINTRIVANI Station: Completed are works for the installation of the equipment intended for the access control and intrusion detection system, the fire-detection system and works for the installation of the equipment in the Station Master Room. In progress are electrical connection works and testing in all installed electromechanical systems.
- PANEPISTIMIO Station: Completed are works for the installation of the equipment in the Station Master Room, as well as works for the installation of the access control and intrusion detection system. In progress are works for the installation of the irrigation system in the surrounding area, works for the installation of steel panel lining at the indoor escalators, as well as testing of all installed electromechanical systems.
- PAPAFI Station: Completed are works for the installation of the equipment in the Station Master Room. In progress are works for the installation of the glass panes at the station sheds, works for the lining of the stonework of Papafi fencing using decorative bricks, works for the completion of the installation of the access control and intrusion detection system, works for the insulation of pipes of the ceiling fan coil units of the ventilation/ air conditioning system in technical rooms and in personnel areas, as well as testing of all installed electromechanical systems.
- EFKLIDIS Station: Completed are painting works at the ventilation shafts, reinstatement works at street-level, in the area of the worksite power substation and works for the installation of the equipment in the Station Master Room. In progress are works for the construction of earthing and testing of all installed electromechanical systems.
- FLEMING Station: Completed are works for the installation of the equipment in the Station Master Room and works for the connection of the ventilation/ air conditioning units with the control panel of the BACS. In progress are works for the installation of steel panels at the bottom side of the escalators, works for the insulation of pipes of the ceiling fan coil units of the ventilation/ air conditioning system in technical rooms and in personnel areas, reinstatement works at street-level in the area of Ekavis Park, as well as testing of all installed electromechanical systems.
- ANALIPSI Station: Completed are works for the installation of the equipment in the Station Master Room, as well as works for the installation of raised floors in technical rooms. In progress is the testing of the installed electromechanical systems.
- 25 MARTIOU Station: Completed are works for the installation of raised floors in technical rooms and works for the installation of false ceilings. Continued are cladding works using aluminum panels works for the construction of fire dampers, as well as testing of the installed electromechanical systems.
- VOULGARI Station: Completed are the works for the installation of raised floors in technical rooms and the installation of glass panes in the indoor lift. In progress are cladding works using aluminum panes in the concourse areas, as well as testing of the installed electromechanical systems.
- NEA ELVETIA Station: Completed are works for the electrical connections of the lighting switchboards and the installation of raised floors in technical rooms. In progress are cladding works using aluminum panels in public areas, works for the installation of lighting system cabling, works for the connection of the ventilation/ air conditioning system’s equipment, works for the installation and connection of cabling of jet fans in the tunnel between the station and the Depot, as well as testing of the electromechanical systems installed.
DEPOT
- Building Complex Ι: With regard to electromechanical installations, in progress are works for the installation of the Building Automation Control System, as well as works for the installation of the equipment of the access control and intrusion detection system.
- Building Complex ΙΙ: With regard to the Administration Building and the Control Centre, completed are works for the installation of the outdoor aluminum glass panels, while in progress are works for the installation of stainless steel lining on the walls of the lifts at all levels, as well as slab paving works at the central yard. In building 2, completed are works for the installation of the ladder at the rain water pumping station and waterproofing works in the planted areas at the south of Building 2. In progress are works for the installation of glass panels and indoor aluminum glass panes, works for the installation of outdoor aluminum louvers and works for the installation of balustrades in the outdoor staircases. With regard to the electromechanical works, in progress are insulation works of the ventilation/air conditioning system’s pipes, works for the installation of air ducts in Building 3, works for the installation of natural gas supply pipes, works for the construction of the pipe and vane network, works for the installation of a fan coil units and works for the installation of the telecommunications equipment system. In the surrounding area, in progress are roadworks / asphalt works and works for the construction of sidewalks in the local streets R11, R2, R4 and R5, wall painting works and works as works for the construction of the new access for the transportation of trains.
- TRACKWORK: Completed are works for the construction of the trackwork and works for the installation of third rail in the entire project.
- In progress are testing and commissioning works.