Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

December 2023

Καλαμαριά Δεκέμβριος 2023
  • Kritis Shaft: In progress are works for the installation of lighting and low voltage cable distribution trays.
  • NOMARCHIA Station: In progress are works for the implementation of the final traffic reinstatement (configuration of sidewalks at Andrianoupoleos street) as well as works for the installation of stainless steel balustrades and glass panes at the platform level.
  • KALAMARIA Station: In progress are works for the installation of stainless steel balustrades and glass panes at stainless steel rails.
  • MIKRA Station: In progress are road paving and slab paving works at street level, while PSD testing activities were repeated. Moreover, in progress are works for the installation of trays at Mikra 1st

TUNNELS: In progress are works for the installation of 3rd Rail’s cable terminations. In addition, in progress are geometric control works for turnouts and crossovers, as well as works for the installation of trays from the Mikra 2nd Crossover up to the Forestation.

WCAG