Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

January 2024

Καλαμαριά Ιανουάριος 2024

• NOMARCHIA Station: In progress are works for the implementation of the final traffic reinstatement (configuration of sidewalks at Andrianoupoleos street) as well as works for the installation of stainless steel balustrades and glass panes on stainless steel rails at the platform level.
• KALAMARIA Station: In progress are works for the installation of stainless steel balustrades and glass panes at stainless steel rails.
• MIKRA Station: In progress are road paving and slab paving works at street level, while PSD testing activities were repeated. Moreover, in progress are works for the installation of cable trays at Mikra 1st Crossover.
Trackwork: In progress are works for the installation of the 3rd rail cable terminations. In addition, in progress are geometric control works for turnouts and crossovers, as well as works for the installation of trays from Mikra 2nd Crossover up to the Forestation.

Print Friendly, PDF & Email
WCAG