Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

February 2024

Θεσσαλονίκη Φεβρουάριος 2024

• NEW RAILWAY Station: Completed are the works for the reinstatement of the central traffic island of the street in the forestation area. In progress are the works for the reinstatement of the southern section of Monastiriou Street, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works for the connection of cables of the BACS equipment, works for the installation of ACC/IDS system, as well as works for the electrical connections of the lighting switchboards.
• DIMOKRATIAS Station: Completed are works for the installation of false ceilings, while in progress are works for the installation of stainless steel cladding in the concourse areas, works for the electrical connections of the mimic and lighting panels, works for the connection of the BACS equipment, the installation of the telecommunications equipment, as well as works for the installation of equipment’s earthing.
• VENIZELOU Station: Completed are works for the installation of granite slab paving works at the transfer level, as well as the works for the construction of the roof slab at the northern access. In progress are works for the execution of vertical marble cladding works at level -3 and the staircase, works for the installation of the air-ducts of the ventilation system, works for the installation of the indoor lift and works for the installation of the fire-detection and the ACC/IDS system. In addition, in progress are the works for the installation of metal cladding of the inner escalators, the drilling of holes for the suspension of the pedestrian bridge overlooking the archaeological site, as well as works for the installation of trays, cables and the construction of earthing. Finally, in progress are works for the placing back and preservation of the archaeological finds / units at level -1 and at the southern access.
• AGIAS SOFIAS Station: In progress are works for the installation of steel cladding panels in public areas, the construction of false ceilings made of fiber-boards, cabling and connections of the lighting system, the connections of the mimic panels and the BACS system related equipment, works for the installation of the equipment intended for tunnel ventilation system, as well as works for the installation of the external lift and the telecommunications equipment.
• SINTRIVANI Station: In progress are the testing activities of all installed electromechanical systems.
• PANEPISTIMIO Station: In progress are the testing activities of all installed electromechanical systems.
• PAPAFI Station: In progress are works for the construction of sheds at street level, as well as the testing activities of all installed electromechanical systems.
• EFKLIDIS Station: In progress are the testing activities of all installed electromechanical systems.
• FLEMING Station: In progress are the testing activities of all installed electromechanical systems.
• ANALIPSI Station: In progress are the works for the construction of the access shed (installation of aluminum panels), as well as the testing activities of all installed electromechanical systems.
• 25 MARTIOU Station: In progress are the testing activities of all installed electromechanical systems.
• VOULGARI Station: In progress are works for the installation of cladding using aluminum panels, the installation of stainless steel balustrades, as well as the testing activities of all installed electromechanical systems.
• NEA ELVETIA Station: In progress are the works for the connection of the minim panels of the jet fans of the tunnel to the depot, as well as the testing activities of all installed electromechanical systems.
DEPOT
• Building Complex IΙ: Completed are the works for the installation of the fire detection system at building #9, as well as the construction of the ventilation/air-conditioning system. In progress are painting works, works for the manufacturing of partitions and gypsum board cladding, works for the installation of cables and lighting fixtures, installation of trays and cables of the distribution system, works for the connection of the uninterrupted power supply items of equipment, installation of air-ducts and the construction of A/C pipes’ insulation, cabling of the telecommunications equipment, as well as works for the installation of the items of equipment intended for train painting activities.
In progress are testing and commissioning works.

Print Friendly, PDF & Email
WCAG