• NOMARCHIA Station (Station and Crossover): In the area of the Crossover, completed are the works for the installation of the elevated floor in the signalling equipment room.
• KALAMARIA Station: In progress are works for the installation of glass panes at stainless steel rails, PSN tiles at the platform level, as well as the installation of side shed covers at the eastern and western accesses. Moreover, in progress are the works for the installation of cladding at the external escalators, while completed are the works for the installation of the elevated floor in the signalling equipment room.
• ARETSOU Station: In progress are the reinstatement works at street level, while completed are the works for the installation of the elevated floor in the signalling equipment room.
• NEA KRINI Station: In progress are the works for the installation of cladding at the external escalators.
• MICRA Station: In progress are the reinstatement works at street level and the installation of cladding at the external escalators.
• TRACKWORK: In progress are works for the installation of the 3rd rail cable terminations. In addition, in progress are geometric control works for turnouts and crossovers, as well as works for the installation of trays from Mikra 2nd Crossover up to the Forestation.