• NEW RAILWAY Station: Completed are the works for the reinstatement of the southern section of Monastiriou Street, works for the construction of the terminations of the west shaft, as well as the installation of stainless steel balustrades at street level. Moreover, the LAS has been activated. In progress are the works for the construction of masonry wall at the west shaft, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works for the connection of cables of the BACS equipment, works for the installation of ACC/IDS system, as well as works for the electrical connections of the lighting switchboards.
• DIMOKRATIAS Station: Completed are works for the installation of air ducts of the ventilation/Air Conditioning system, the installation of aluminum panels, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works for the connection of cables of the BACS equipment, works for the installation of ACC/IDS system, as well as works for the electrical connections of the lighting switchboards, the installation of the telecommunications equipment, as well as works for the activation of the LAS substation. In progress are works for the installation of steel cladding in the concourse areas, the installation of lighting fixtures, as well as works for the earthing of equipment.
• VENIZELOU Station: Completed are cladding works using ceramic tiles in WCs and the pumping station, vertical marble cladding works in the concourse areas, works for the installation of metal cladding of the inner escalators, works for the installation of the indoor lift, works for the construction of the sound proofing system of the tunnels’ east ventilation equipment shaft, the building works, as well as the installation of the furniture in the Station Master Room, the architectural works – stage A’ at the north access, as well as concreting works of the exterior shaft of the lift at the south access. In progress are works for the dismantling of asphalt paving – existing sidewalks and works for the installation of curbs and sidewalk slabs at the north side of Egnatia Street, works for the construction of false ceilings at the station, painting works, architectural works – stage A’ at the south access, works for the installation of STO sub-base at the station, works for building the pedestrian bridge overlooking the archaeological site, as well as works for the installation of the air-ducts and outlets of the ventilation/air conditioning system. In progress are works for the installation of the firefighting system, the fire detection system and the ACC/IDS system, works for the installation of the equipment at the east tunnel ventilation shaft, as well as works for the installation of trays, cables, the lighting system and the construction of earthing. Moreover, in progress are works for the placing back and preservation of the archaeological finds / units at level -1, while completed are the respective works for placing back antiquities at the southern access.
• AGIAS SOFIAS Station: Completed are works for the installation of steel cladding panels in public areas, the installation of stainless steel handrails, the construction of false ceilings, the installation of knock-out balustrades, the installation of the automatic extinguishing system using gas in technical rooms, as well as the activation of the LAS. In progress are cabling and connections of the lighting system, the connections of the mimic panels and the BACS system related equipment, works for the installation of the fire detection system, works for the installation of equipment intended for tunnel ventilation system, as well as works for the installation of the external lift and the telecommunications equipment.
• SINTRIVANI Station: In progress are the testing activities of all installed electromechanical systems.
• PANEPISTIMIO Station: In progress are the testing activities of all installed electromechanical systems.
• PAPAFI Station: In progress are works for the construction of sheds at street level, as well as the testing activities of all installed electromechanical systems.
• EFKLIDIS Station: In progress are the testing activities of all installed electromechanical systems.
• FLEMING Station: In progress are the testing activities of all installed electromechanical systems.
• ANALIPSI Station: In progress are the works for the construction of the access shed (installation of aluminum panels), as well as the testing activities of all installed electromechanical systems.
• 25 MARTIOU Station: In progress is the waterproofing over the temporary openings of the junction area of Kalamaria extension, as well as the testing activities of all installed electromechanical systems.
• VOULGARI Station: Completed are the works for the installation of cladding using aluminum panels, the works for the installation of stainless steel balustrades, while in progress are the testing activities of all installed electromechanical systems.
• NEA ELVETIA Station: Completed are the works for the connection of the mimic panels of the jet fans of the tunnel to the depot, as well as the respective testing activities, while in progress is the testing of all installed electromechanical systems.
DEPOT
• Building Complex Ι: In progress are works for the application of polyurethane paint at the workshops’ floors, while completed is the installation of equipment at the train painting related facility.
• Building Complex IΙ: Completed are the connections of the general LV switchboard at building #9, while in progress are painting works, aluminum construction related works, works for the construction of false ceilings, works for the installation of cables of the distribution, lighting and BACS systems, as well as works for the connection of the uninterrupted power supply items of equipment. In progress are the works for the installation of air ducts and the construction of A/C pipes’ insulation, the works for the installation of inlets of the ventilation – A/C system, the installation of the ACC/IDS system, cabling of the telecommunications equipment, as well as works for the installation of the fire detection system. Moreover, completed are the works for the installation and connection of the storm-water pumping unit in the surrounding area.
In progress are testing and commissioning works.