Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Θεσσαλονίκη Απρίλιος 2024

• NEW RAILWAY Station: Completed are the works for the installation of stainless steel and the testing of the low voltage distribution system. In progress are architectural finishes works at the western shaft, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works for the connection of cables of the BACS equipment. In addition, in progress are works for the installation of the fire detection and ACC/IDS systems, works for the installation of the telecommunications equipment, works for the electrical connections of the lighting switchboards, as well as the testing activities for the tunnel ventilation system.
• DIMOKRATIAS Station: Completed are works the installation of the telecommunications equipment; in progress are the works for the completion of the lighting and ventilation/Air Conditioning systems. In addition, completed are the testing activities of the low voltage distribution system and the testing activities of the pumping station equipment of the Station.
• VENIZELOU Station: Completed are the testing activities of the low voltage distribution system, as well as the sidewalk reinstatement works at street level. In progress are works for the construction of false ceilings at the station, painting works, architectural works – stage A’ at the south access, works for the installation of STO sub-base at the station. In progress are works for building the pedestrian bridge overlooking the archaeological site, as well as works for the installation of the ventilation/air conditioning system, works for the installation of the firefighting system, the fire detection system and the ACC/IDS system. Finally, in progress are works for the installation of the equipment of the tunnels’ ventilation shafts, works for the connection of the lighting switchboards and mimic panels, as well as the works for the installation of trays, cables, the lighting system and the construction of earthing. Moreover, in progress are works for the placing back and preservation of the archaeological finds / units at level -1.
• AGIAS SOFIAS Station: Completed are works for the installation of the telecommunications equipment, the testing activities for the low voltage distribution system, for the pumping station equipment, as well as the testing activities of the outdoor lift. In progress are cabling and connections of the lighting system, the connections of the mimic panels and the BACS system related equipment, works for the installation of the ACC/IDS system, testing activities for tunnel ventilation and ventilation-A/C systems.
• SINTRIVANI Station: In progress are the BACS related testing activities of all installed electromechanical systems.
• PANEPISTIMIO Station: In progress are the BACS related testing activities of all installed electromechanical systems.
• PAPAFI Station: In progress are works for the completion of the sheds’ construction at street level, as well as the BACS related testing activities of all installed electromechanical systems.
• EFKLIDIS Station: In progress are the BACS related testing activities of all installed electromechanical systems.
• FLEMING Station: In progress are the BACS related testing activities of all installed electromechanical systems.
• ANALIPSI Station: In progress are the works for the construction of the access shed (installation of aluminum panels), the in-house testing of the ACC/IDS system and the automatic extinguishing system using gas, as well as the BACS related testing activities of all installed electromechanical systems.
• 25 MARTIOU Station: In progress are the reinstatement works at street level, the in-house testing of the automatic extinguishing system using gas, as well as the BACS related testing activities of all installed electromechanical systems.
• VOULGARI Station: In progress is the in-house testing of the automatic extinguishing system using gas, as well as the BACS related testing activities of all installed electromechanical systems.
• NEA ELVETIA Station: In progress are the works for the completion of the installation and control of the fire detection system, the in-house testing of the automatic extinguishing system using gas, as well as the BACS related testing activities of all installed electromechanical systems.
DEPOT
• Building Complex Ι: In progress are works for the application of polyurethane paint at the workshops’ floors.
Building Complex IΙ: In progress are painting works, aluminum construction related works, works for the construction of false ceilings, works for the installation of cables of the distribution, lighting and BACS systems, as well as works for the connection of the uninterrupted power supply items of equipment. In progress are the works for the installation of air ducts and the construction of A/C pipes’ insulation, the works for the installation of inlets of the ventilation – A/C system, the installation of the ACC/IDS system, cabling of the telecommunications equipment, as well as works for the installation of the fire detection system.
In progress are testing and commissioning works.

Print Friendly, PDF & Email
WCAG