Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Θεσσαλονίκη Μάιος 2024

• NEW RAILWAY Station: Completed are the works for the installation of elevated floors at technical rooms, works for the installation of false-ceilings, works for the electrical connections of the mimic panels of the tunnel ventilation and ventilation/air-conditioning systems, works for the connection of cables of the BACS equipment, works for the installation of the ACC/IDS system, as well as works for the installation of the telecommunications equipment. In progress are reinstatement works at street level, as well as the BACS related testing activities of all installed electromechanical systems.
• DIMOKRATIAS Station: Completed are works the installation of granites at the parapet walls of the entrances terminations, works for the installation of the exterior roller shutters, works for the installation of the lighting and the ACC – IDS systems, as well as works for setting the fans of the tunnel ventilation system in operation. In progress are the BACS related testing activities of all installed electromechanical systems.
• VENIZELOU Station: Completed are the works for the installation of the escalators at the northern and southern entrances. In progress are works for the construction of false ceilings at the station, the installation of granites at the southern entrance, works for the installation of STO sub-base at the station, as well as works for building the pedestrian bridge overlooking the archaeological site. Moreover, in progress are works for the placing back and preservation of the archaeological finds / units at level -1 and at the entrances.
AGIAS SOFIAS Station: Completed are works for cabling and connections of the lighting system, the connections of the mimic panels and the BACS system related equipment, works for the installation of the ACC/IDS system. In progress are the BACS related testing activities of all installed electromechanical systems.
• SINTRIVANI Station: Completed are works for the installation of the outdoor cladding on the walls of the southern entrance, planting works and works for the installation of the irrigation system as well as the final painting works. In progress are the BACS related testing activities of all installed electromechanical systems.
• PANEPISTIMIO Station: Completed are the final painting works, as well as the planting works and works for the installation of the irrigation system. In progress are the BACS related testing activities of all installed electromechanical systems.
PAPAFI Station: At the completion stage are works for the construction of the sheds at street level, as well as the BACS related testing activities of all installed electromechanical systems.
• EFKLIDIS Station: Completed are works for the construction of the exterior fencing using perforated panels and in progress are the final painting works, as well as the BACS related testing activities of all installed electromechanical systems.
• FLEMING Station: In progress are the BACS related testing activities of all installed electromechanical systems.
• ANALIPSI Station: Completed are the final painting works and the works for the removal of DEDDHE substation. In progress are the works for the construction of the access shed, as well as the BACS related testing activities of all installed electromechanical systems.
• 25 MARTIOU Station: In progress are the reinstatement works at street level, as well as the BACS related testing activities of all installed electromechanical systems.
• VOULGARI Station: Completed are the works for the removal of DEDDHE substation. In progress are works for the completion of the false ceilings, as well as the BACS related testing activities of all installed electromechanical systems.
• NEA ELVETIA Station: Completed are the works for the installation and control of the fire detection system, while in progress are the BACS related testing activities of all installed electromechanical systems.
DEPOT
• Building Complex IΙ: In progress are painting works, aluminum construction related works, works for the construction of false ceilings, works for the installation of cables of the distribution system, the works for the installation of air ducts and the construction of A/C pipes’ insulation, the works for the installation of inlets of the ventilation – A/C system, the installation of the ACC/IDS system, cabling of the telecommunications equipment, as well as works for the installation of the fire detection system.
In progress are testing and commissioning works.

WCAG