Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
Καλαμαριά Μάιος 2024
  • KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, the installation of glass panes at stainless steel rails, as well as works for the installation of PSN tiles at level (-1).
  • ARETSOU Station: Completed are works for the stripping of Kanari Street, while in progress are works for the installation of cable supports of the traction system.
  • NEA KRINI Station: Completed are cladding works at the escalators.
  • MICRA Station (Station and Crossovers): In progress are the reinstatement works at street level, lighting cabling works in the concourse area, as well as works for the installation of cable supports of the traction power supply system in the crossover area.
  • TRACKWORK: In progress are geometric control works for the acceptance of the 3rd rail and ultrasound control of aluminothermic welding at the section Beginning of the Project – NOMARCHIA Station. In addition, completed are works for the installation of seismic support plates in the areas of the floating slabs, the installation of smooth reinforcement for bridging the bars of the stray current tray, as well as the final geometric control of the installed tracks.
Print Friendly, PDF & Email
WCAG