Καλαμαριά Ιούνιος 2024
  • NOMARCHIA Station: Completed are works for the reinstatement of sidewalks and bollards for the protection of pedestrians on Mitropolitou Kydonion street.
  • KALAMARIA Station: In progress are works for the installation of covers of sheds and roller shutters, as well as works for the installation of PSN tiles at level 0.
  • MICRA Station (Station & Crossovers): In progress are surface reinstatement works at the station and at the two crossovers, as well as cabling works of the fire detection system. Moreover, completed are works for the installation of shaft covers at the platform level.
  • TRACKWORK: In progress are geometric control works for the acceptance of the 3rd rail and ultrasound control of aluminothermic welding at the section Beginning of the Project – NOMARCHIA Station. Welding related failures – as revealed by the ultrasound control (KP 2+897 & 2+888 Track 1) – have been repaired. In progress are the control and cleaning of drainage pits at track level, as well as maintenance works and trackbed concrete cleaning works.