• NEW RAILWAY Station, DIMOKRATIAS Station, AGIAS SOFIAS Station, SINTRIVANI Station, PANEPISTIMIO Station, PAPAFI Station, EFKLIDIS Station, FLEMING Station, ANALIPSI Station, 25 MARTIOU Station, VOULGARI Station, NEA ELVETIA Station: In progress are the BACS related testing activities of all installed electromechanical systems.
• VENIZELOU Station: Completed are the works for the completion of the construction of false ceilings, works for the installation of floor granites and the construction of a lift at the south access, works for the installation of stainless steel handrails and glass panes, works for the installation of the telecommunications equipment, works for the installation of trays and cables, works for the construction of earthing, as well as mechanical works at the two accesses. In addition, in progress are the works for the preservation of the archaeological finds / units at level -1 and at the entrances, as well as the stand-alone tests of the installed electromechanical equipment.
• NEA ELVETIA Station: In progress are earthworks, as well as roadworks for opening M. Psellou street, in the framework of the station’s supporting works. Moreover, in progress are works for the bus transfer station.
DEPOT:
• Building Complex IΙ: In progress are painting works, works related to aluminum structures, works for the construction of false ceilings, works for the installation of cables of the distribution system, lighting & BACS, works for the installation of air ducts and works for the construction of insulation of A/C pipes, works for the installation of the access control and intrusion detection system, cabling of the telecommunications equipment, as well as works for the installation of the fire detection system.
In progress are testing and commissioning works.