August 2024

Καλαμαριά

NOMARCHIA Station: In progress are cabling inspection works of the fire detection system.
ARETSOU Station: In progress are works for the installation of floor granites at the platform level as well as cabling inspection works of the fire detection system.
NEA KRINI Station: In progress are cabling inspection works of the fire detection system.
TRACKWORK: In progress are measurements of the safety related dimensions of turnouts and crossovers, as well as gauge controls and guard rail controls, works for the installation of the forestation buffer and their final tuning, as well as inspection works of the drainage shafts at track level.