• NEW RAILWAY Station, DIMOKRATIAS Station, AGIAS SOFIAS Station, SINTRIVANI Station, PANEPISTIMIO Station, PAPAFI Station, EFKLIDIS Station, FLEMING Station, ANALIPSI Station, 25 MARTIOU Station, VOULGARI Station, NEA ELVETIA Station: In progress are the BACS related testing activities of all installed electromechanical systems.
• VENIZELOU Station: In progress are street-level reinstatement works, works for the completion of the construction of false ceilings, works for the construction of the entrance sheds, works for the installation of floor granites, painting works, works for the completion of the installation of the telecommunications equipment as well as electromechanical works at the two accesses. In addition, in progress are the works for the preservation and display of the archaeological finds / units at level -1 and at the entrances, as well as the stand-alone tests of the installed electromechanical equipment and the BACS tests of all installed electromechanical systems.
• NEA ELVETIA Station: In progress are works for the installation of seats at platform level, works for the installation of sanitary appliances, works for the installation of ironmongery, as well as BACS tests of all installed electromechanical systems. Moreover, at street-level, in progress are works for the implementation of the accompanying supporting works for ensuring the services to moving passengers, as well as their transfer.
DEPOT:
• Building Complex IΙ: In progress are works for the installation of cables of the distribution system, lighting & BACS, as well as works for the installation of air ducts and works for the construction of insulation of A/C pipes, works for the installation of the access control and intrusion detection system, cabling of the telecommunications equipment, as well as works for the installation of the fire detection system.
• In progress are testing and commissioning works.