September 2024

NOMARCHIA Station (Station & Crossover): Works for the reinstatement of sidewalks and bollards in Mitropolitou Kydonion Street have been executed. In progress are cabling inspection works of the fire detection system.
KALAMARIA Station: In progress are works for the installation of PSN tiles at level 0, shed and roller shutter coating.
MICRA Station: In progress are cabling works of the fire detection system.
TRACKWORK: In progress are measurements of the safety related dimensions of turnouts and crossovers, as well as gauge controls and guard rail controls, works for the installation of the forestation buffer and their final tuning, as well as inspection works of the drainage shafts at track level. Moreover, MV cables have been installed from NOMARCHIA to NEA ELVETIA Stations.