November 2024

Καλαμαριά Νοέμβριος 2024

Works for the upgrading of the PSD earthing system, as well as inspection works for the installation of the fire detection system are being executed in all stations.  Moreover, preparatory works for the installation of fibre optics are being executed.

  • NOMARCHIA Station: In progress are the Medium Voltage System related works.
  • NEA KRINI Station: In progress are the architectural finishes, as well as the Medium Voltage System related works.
  • MIKRA Station: In progress are the works related to the Medium Voltage System distribution, as well as road surface reinstatement works.
  • TBM TUNNELS – TRACKWORK: In progress are waterproofing works and the works in the sockets boards of the lighting system.