November 2015

  • KORYDALLOS Station: The works for the waterproofing of the station are in progress.
  • MANIATIKA Station: The excavation and temporary retaining works of phase A1 (eastern gallery) and phase A2 of the southern front of the station’s main tunnel are in progress.
  • PIRAEUS Station: The preparation works for the construction of diaphragm walls is in progress. The archaeological excavation works are in progress in the Shaft.
  • DIMOTIKO THEATRO Station: The Phase A excavation works (36m/140m already excavated), as well as the Phase B excavation works (32m/140m already excavated) at the triple track NATM tunnel towards the University of Piraeus are in progress.
    At Panepistimio shaft, the archaeological investigation in the PUO network diversion areas is in progress. The works for the maintenance of TBM and the partial relocation of the TBM worksite are in progress.
    The tunnel excavation has been completed by 50.47%.