August 2015

  • AGHIA VARVARA Station: The construction works and the works for stressing the prestressed anchors at Taxiarchon Shaft are about to be completed;
  • KORUDALLOS Station: The works for waterproofing the station are in progress;
  • NIKEA Station: The TBM maintenance works are in progress;
  • PIRAEUS Station: The works for the construction of part of the rainwater network are at an advanced stage;
  • DIMOTIKO THEATRO Station: In progress are the works pertaining to the conservation of the archaeological finds and to the preparation of the exhibition area for the revealing and promotion of these finds in the building located at Pylon street, property of the Department of Antiquities;
  • Tunnel boring works have been completed by 50%.