  • AGHIA VARVARA Station: The works for the construction of columns down to the concourse level have been completed, while the works for the construction of access 3 are in progress;
  • KORYDALLOS Station: The removal of the launch cradle and the TBM false tunnel precast segments has been completed. The undisturbed cutting of the precast segments for TBM drive are in progress;
  • NIKEA Station: The works for the concreting of fixed staircases and escalators nos. 1, 2, 3, 4, 8, 9 from the platform level to the mechanical floor slab level have been completed. Completed are also the works for the concreting of staircase no. 5 (level +7.00 down to +13.12), no. 6 (level +6.90 down to +24.17) and no. 7 (level +6.90 down to +24.26). The works for the construction of mezzanine floor at the concourse level (level +16.22). TBM maintenance works are in progress;
  • MANIATIKA Station: In progress are works for the 12th level of the Station’s main building and for the application of shotcrete at the 11th level in the c/c area at Mavromichali street. The works for the conversion of the PPC network into an underground network and for reinstating part of the paving at the north sidewalk at Gythiou street have been completed;
  • PIRAEUS Station: Completed are the works related to the dismantling of old networks, while in progress are the works for the construction of part of the stormwater network;
  • DIMOTIKO THEATRO Station: The works related to the waterproofing and the concreting of the foundation slab and the perimeter walls down to the platform level of the main Station are in progress. At the entrance on Korai square in progress is the installation of a temporary retaining system (shotcrete – prestressed anchors – struts), the works for the excavation of the 3rd bottom (+1.00). Moreover, completed is the construction of temporary retaining piles at the Station entrance (31/33) on P. Bakogianni square. Phases A’ and B’ of the excavation works (progress of excavation works 18m/140m) were completed at the triple track NATM tunnel towards the University of Piraeus; phase A of the excavation works (progress of excavation works 18m/140m) is in progress (progress rate: 27/63m) towards Dimotiko Theatro (Municipal Theatre);
  • Tunnel excavation works have been completed by 50%.