Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

December 2014

  • AGHIA VARVARA Station: The works for the construction of columns up to the mechanical floor level are in progress;
  • KORYDALLOS Station: Concreting works of the foundation slab and the perimeter walls of the Station up to the concourse level are in progress;
  • NIKEA Station: The works for the construction of the Station’s permanent lining are in progress (concreting of exterior perimeter walls and columns from level -3 of the platforms up to level -2 of the concourse slab, from level -2 of the concourse slab up to level -1 of the E/M slab, as well as concreting of the concourse slab);
  • MANIATIKA Station: The following works are in progress: Excavation and shotcreting of the Station’s main building at levels 6, 7, 8, 9, 10 and 11, construction of prestressed anchors of the Station’s main building at level 8, as well as works for the construction of fully embedded rock anchors in the C/C area at Petr. Mavromichali street. Excavation and temporary retaining works at the access chamber were completed, while excavation and temporary retaining works are in progress in the Station’s main tunnel (phase A1 – southern section – eastern gallery);
  • PIRAEUS Station: Foul water sewage works are in progress, while in the framework of traffic arrangement, works for the construction of ILPAP network and sidewalks are in progress;
  • DIMOTIKO THEATRO Station: The excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) is in progress at excavation level 7 (-15.00), except the access ramp area at Aghiou Konstantinou square. The following works are in progress: excavation and temporary retaining at level 3 of Deligianni shaft, dismantling at Tsamadou street section for the diversion of PUO networks at Panepistimio shaft, as well as archaeological investigation works in the dismantling areas;
  • The tunnel boring machine is under maintenance at KORYDALLOS Station, while excavation works are expected to commence in the immediate future.
WCAG