Web Portal - Elliniko Metro A.E.
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa
ELLINIKO METRO A.EELLINIKO METRO A.EELLINIKO METRO A.E logo espa

October 2014

  • AGHIA VARVARA Station: The works for the construction of supporting columns up to the concourse level were completed, while the works for the construction of beams and the concourse slab are in progress. Moreover, the works for the construction of piles at Taxiarchon shaft are in progress;
  • KORYDALLOS Station: The works for the waterproofing of the Station up to the roof level, as well as the reinforcement and concreting works at the concourse level are in progress;
  • NIKEA Station: The works for the temporary drainage and waterproofing of the NATM tunnel invert of the main Station were completed. The works for the construction of the permanent lining of the main Station (exterior perimeter parapet walls and columns at level -3 of the platforms up to level -2 of the concourse slab) are in progress;
  • MANIATIKA Station: The works for the excavation and temporary retaining of the Station’s main building, as well as the excavation and temporary retaining works in the main Station tunnel are in progress;
  • PIRAEUS Station: The works for the diversion of OTE optic fibre networks and other providers, PPC and storm water networks are in progress. In the framework of traffic arrangements, the works for the construction of the traffic signalling network are in progress. The investigation trench for the identification of the foundations of the pedestrian bridge, as well as the investigation trenches in view of confirming ISAP building foundation items are in progress;
  • DIMOTIKO THEATRO Station: The excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) are in progress at the 5thexcavation level (-4.00), except for the access ramp area at Aghiou Konstantinou square. The excavation and temporary retaining works at the 1st level, at Deligianni Shaft, and the works for the installation of signs in the framework of implementing the traffic arrangements for the occupation of Tsamadou street, at Panepistimio Shaft, are in progress;
  • The tunnel excavation has been completed at a proportion of 26%.
WCAG