September 2014

  • AGHIA VARVARA Station: The works for the construction of supporting columns up to the platform level were completed, while the works for the construction of parapet walls and the platform floor are in progress;
  • NIKEA Station: The works for the temporary drainage of the final excavation floor of the main Station, the waterproofing of the foundation slab of the main Station, as well as the excavation and retaining of the NATM tunnel of the Station were completed (Phase A’). The works for the waterproofing of the exterior perimeter parapet walls, the construction of the permanent lining of the main Station (concreting of the foundation slab at level -3 of the platforms) and the excavation and retaining of the Station’s NATM tunnel (Phase B’) are in progress;
  • MANIATIKA Station: The works for the excavation up to level 11, the laying of shotcrete at levels 4, 8 and 10 and the construction of prestressed anchors at level 4 of the Station’s main building are in progress;
  • PIRAEUS Station: The works for the routing of OTE optic fibre networks, various suppliers and PPC at the northern side are in progress. In the framework of traffic arrangements, the construction of road and asphalt pavings, the construction of the temporary fencing wall in OLP area and the installation of balustrades in OLP area have been completed. The works for the extension of the worksite occupation / fencing, the construction of sidewalks and traffic islands, the installation of traffic signs and the construction of traffic diversion parapet wall are in progress;
  • DIMOTIKO THEATRO Station: The excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) were completed at the 3rdexcavation bottom (+2.00), while the excavation and installation of the temporary retaining system (shotcrete – prestressed anchors) at the 4th excavation level at Aghiou Konstantinou square are in progress. The works for the construction of temporary retaining piles have been completed, while the construction of a cap beam at Deligianni shaft and the archaeological excavation at the ventilation shaft are in progress;
  • The tunnel excavation has been completed at a proportion of 22%.