October 2013

  • The works for the construction of the foundation slab at the TBM start-up shaft have been completed;
  • The works for the construction of the pile cap beam of AGHIA VARVARA Station are in progress;
  • The works for the excavation and the temporary retaining of KORYDALLOS Station are in progress;
  • The works for the construction of piles and the pile cap beam of NIKEA main Station have been completed, while the works for the construction of the entrances’ piles are in progress;
  • The Archaeological investigation in the section under occupation has been completed, while the investigation of the archaeological wells/reservoirs in P. Bakoyianni Square in the area of DIMOTIKO THEATRO is in progress;
  • The traffic arrangement for the construction of MANIATIKA Station is in progress;
  • The worksite occupation (Phase A’) is at the completion stage, while the configuration of the occupation boundaries to the southern side of Odyssou Square in the area of PIRAEUS Station is in progress.