September 2013

  • The excavation and retaining works of the NATM tunnel towards Piraeus at the TBM Access Shaft, as well as the drainage and waterproofing of the shaft’s bottom have been completed;
  • The excavation works in AGHIA VARVARA Station are in progress, while the construction works for temporary retaining piles have been completed;
  • The Piles and the Pile cap beam of the main Station, as well as the configuration of the new roadwork ar the perimeter of Eleftherias Square in KORYDALLOS Station have been completed;
  • The worksite occupation and the fencing, as well as the archaeological excavation in the open cut area on Petr. Mavromichali Street in MANIATIKA Station are in progress.